[SMM PV Flash] The Ordos 4 million kW new energy project transmission project at the Kubuqi Desert Base, a core supporting new energy delivery project for the Mengxi-Tianjin South UHV corridor, has achieved full-line connection.
On October 24, as the last conductor was pulled into place at tower position A76, the transmission project for the 4 million kW new energy base in Ordos, located in the Kubuqi Desert, completed all stringing work, marking the full connection of this key project serving cross-regional green electricity transmission. The project has now entered the final sprint phase before commissioning.
The project is the core supporting new energy delivery project for the Mengxi–Tianjin South UHV corridor, with a total investment of 1.94 billion yuan. The line starts from the 500 kV Dalu Substation, connects through the newly built 500 kV Bu'ertao Substation, and ultimately feeds into the 1000 kV UHV Ordos Station. A total of two 500 kV substations were newly built along the entire route, with 279 kilometers of 500 kV transmission lines and 340 steel towers erected. Since construction officially began on December 8, 2025, the construction team overcame multiple challenges such as sandstorms and complex terrain within a desert construction window of less than 12 months, efficiently completing all stringing period tasks.