Orion Advances Prieska Copper-Zinc Mine Readiness as DFS Sets Phased Development Plan

Published: Jul 24, 2026 09:48 (GMT+8)

Orion Minerals said it carried out value engineering, operational-readiness work and critical-skills identification for execution of its Prieska copper-zinc mine in South Africa’s Northern Cape. The Prieska mine, near Copperton, is hosted in a volcanogenic massive sulphide deposit.

The project’s definitive feasibility study outlines an accelerated development strategy, beginning with an “Uppers” mining operation at 20,000 tonnes per month, alongside dewatering preparations for the subsequent “Deeps” phase at 200,000 tonnes per month. These are development plans and readiness activities, rather than confirmed production; financing, dewatering, construction decisions and future copper-zinc guidance remain key follow-up items.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
【Flash | Court Ruling Eases Shutdown Risk at Young Poong’s Indium-Bearing Seokpo Smelter】
13 hours ago
【Flash | Court Ruling Eases Shutdown Risk at Young Poong’s Indium-Bearing Seokpo Smelter】
Read More
【Flash | Court Ruling Eases Shutdown Risk at Young Poong’s Indium-Bearing Seokpo Smelter】
【Flash | Court Ruling Eases Shutdown Risk at Young Poong’s Indium-Bearing Seokpo Smelter】
Young Poong Corporation disclosed on October 2 that a court of first instance had cancelled the 10-day suspension order for Seokpo Smelter, which is currently operating normally. Sales attributable to the affected operation totalled approximately KRW 1.0096 trillion in 2024, representing 36.22% of consolidated revenue. Young Poong’s official history shows that the smelter completed an indium plant in April 2012. SMM views the ruling as easing near-term disruption risk to zinc smelting and by-product indium extraction, although any appeal and the indium plant’s actual operating rate and output require further monitoring.
13 hours ago
Downstream consumption shows mediocre performance; SHFE zinc remains in the doldrums [SMM Zinc Futures Briefing]
15 hours ago
Downstream consumption shows mediocre performance; SHFE zinc remains in the doldrums [SMM Zinc Futures Briefing]
Read More
Downstream consumption shows mediocre performance; SHFE zinc remains in the doldrums [SMM Zinc Futures Briefing]
Downstream consumption shows mediocre performance; SHFE zinc remains in the doldrums [SMM Zinc Futures Briefing]
[Downstream consumption mediocre, SHFE zinc in the doldrums] The most-traded SHFE zinc 2611 contract opened at 25,950 yuan/mt. After the open, SHFE zinc consolidated, hitting an intraday high of 25,950 yuan/mt in early trading and a low of 25,715 yuan/mt near the close, before settling down at 25,730 yuan/mt, down 250 yuan/mt or 0.96%. Trading volume increased to 68,235 lots, while open interest fell by 2,871 lots to 97,926 lots.....
15 hours ago
Data: SHFE, DCE market movement (Oct 13)
16 hours ago
Data: SHFE, DCE market movement (Oct 13)
Read More
Data: SHFE, DCE market movement (Oct 13)
Data: SHFE, DCE market movement (Oct 13)
The following table shows the ferrous and nonferrous metals movement on the SHFE and DCE on 13 Oct , 2026
16 hours ago