Orion Advances Prieska Copper-Zinc Mine Readiness as DFS Sets Phased Development Plan

Published: Jul 24, 2026 09:48

Orion Minerals said it carried out value engineering, operational-readiness work and critical-skills identification for execution of its Prieska copper-zinc mine in South Africa’s Northern Cape. The Prieska mine, near Copperton, is hosted in a volcanogenic massive sulphide deposit.

The project’s definitive feasibility study outlines an accelerated development strategy, beginning with an “Uppers” mining operation at 20,000 tonnes per month, alongside dewatering preparations for the subsequent “Deeps” phase at 200,000 tonnes per month. These are development plans and readiness activities, rather than confirmed production; financing, dewatering, construction decisions and future copper-zinc guidance remain key follow-up items.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Teck’s Red Dog Q2 Zinc Output Falls 18% as Mine-Life Extension PFS Advances
1 hour ago
Teck’s Red Dog Q2 Zinc Output Falls 18% as Mine-Life Extension PFS Advances
Read More
Teck’s Red Dog Q2 Zinc Output Falls 18% as Mine-Life Extension PFS Advances
Teck’s Red Dog Q2 Zinc Output Falls 18% as Mine-Life Extension PFS Advances
Teck Resources reported on July 23 that Red Dog processed 1.13 million tonnes of ore in the second quarter, at average grades of 12.3% zinc and 3.8% lead, producing 112,000 tonnes of zinc and 21,900 tonnes of lead. Zinc output declined 18% year on year from 136,600 tonnes, mainly because of lower mill feed grades. Teck expects mining at Qanaiyaq to be completed this year, while Aqqaluk is expected to supply the mill until around 2031, with zinc output set to decline as grades diminish. Although first-half zinc production reached 218,200 tonnes, Teck expects full-year output to remain within guidance as grades continue to decline and the zinc and lead recovery circuits undergo a planned maintenance shutdown in the fourth quarter. Zinc guidance for 2026, 2027 and 2028 stands at 375,000–415,000 tonnes, 330,000–370,000 tonnes and 230,000–270,000 tonnes, respectively. The Red Dog Mine Life Extension PFS is progressing, supported by a substantially completed 12-mile access road, an awarded underground exploration-decline contract and C$200 million–C$250 million of 2026 budgeted spending.
1 hour ago
[SMM Flash] 28,000 mt Sulfur Shipment Vessel's First Discharge at Zhanjiang Port
1 hour ago
[SMM Flash] 28,000 mt Sulfur Shipment Vessel's First Discharge at Zhanjiang Port
Read More
[SMM Flash] 28,000 mt Sulfur Shipment Vessel's First Discharge at Zhanjiang Port
[SMM Flash] 28,000 mt Sulfur Shipment Vessel's First Discharge at Zhanjiang Port
SMM tracking data shows that on July 23, the sulfur vessel LADY ILEEN berthed at Zhanjiang Port for operations. The vessel had a shipment of 28,425 mt, departed from Bahrain on June 21, and was first discharged at Zhanjiang Port on July 23.
1 hour ago
Teck’s Q2 Zinc Gross Profit Rises to $353 Million; Full-Year Zinc Guidance Maintained
1 hour ago
Teck’s Q2 Zinc Gross Profit Rises to $353 Million; Full-Year Zinc Guidance Maintained
Read More
Teck’s Q2 Zinc Gross Profit Rises to $353 Million; Full-Year Zinc Guidance Maintained
Teck’s Q2 Zinc Gross Profit Rises to $353 Million; Full-Year Zinc Guidance Maintained
Teck Resources reported gross profit before depreciation and amortisation of $353 million from its zinc segment for the quarter ended June 30, up from $159 million a year earlier. The improvement reflected higher zinc prices and the continued implementation of an optimised feed strategy at Trail Operations. The company generated $1.7 billion in operating cash flow and ended the quarter with $10.3 billion of liquidity, including $6.1 billion in cash. Teck maintained its full-year zinc production guidance at 410,000–460,000 tonnes, expected to yield 190,000–230,000 tonnes of refined zinc. Further monitoring should focus on Trail Operations’ refined-zinc output, feed availability and delivery against guidance.
1 hour ago