Heavy Rain and Snowfall Trigger Emergency Measures at Multiple Copper Mines in Chile

Published: Jul 24, 2026 08:45

Recently, heavy rainfall and high-altitude snowfall hit central Chile and the Atacama region, prompting multiple copper mines to initiate winter emergency measures.

Los Pelambres, owned by Antofagasta Minerals, temporarily restricted access to the mine site and preemptively scaled back non-critical operations, though no full production suspension has been reported so far. Andina, operated by Codelco, suspended surface operations, while El Teniente halted open-pit ore transport at one point due to hillside snow accumulation.

Among these, Caserones was the most significantly affected. Lundin Mining stated that the mine has been suspended since July 18 due to heavy snow, restricted road access, and an on-site power outage. It is currently relying solely on backup generators to sustain critical activities, and production will resume once power is restored and road access improves. As of July 24, the company had not yet issued a production resumption announcement, but Lundin Mining maintained its full-year production guidance.

Overall, this round of disruptions was concentrated in central Chile and some high-altitude mining areas. The major copper mines in the far north generally maintained operations, and a nationwide large-scale production halt has not materialized. In the near term, attention should continue to be paid to the timing of Caserones' production resumption and the progress in restoring road access and power at the mine site.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
EU Industry Chief Proposes Broad Ban on Waste Exports to Non-OECD Countries
2 hours ago
EU Industry Chief Proposes Broad Ban on Waste Exports to Non-OECD Countries
Read More
EU Industry Chief Proposes Broad Ban on Waste Exports to Non-OECD Countries
EU Industry Chief Proposes Broad Ban on Waste Exports to Non-OECD Countries
The EU's industry chief Stephane Sejourne has decided to propose a broad ban on exports of waste, includingaluminium scrap, to non-OECD countries, a statement from Sejourne's cabinet said on Friday.Sejourne had been expected to present long-awaited trade measures on September 23, which would have only limited exports of aluminiumscrap."In the internal discussions, it appeared that the tool proposed could only cover around a half of the scrap export. As a result, the Executive Vice-President has decided to withdraw the proposal and to explore a proposal, independent from trade instruments," the statement said."We are now working on a delegated act under the Waste Shipment Regulation. This delegated act will ban exports of waste, including aluminiumscrap to non-O
2 hours ago
Data: SHFE, DCE market movement (Sep 07)
8 hours ago
Data: SHFE, DCE market movement (Sep 07)
Read More
Data: SHFE, DCE market movement (Sep 07)
Data: SHFE, DCE market movement (Sep 07)
The following table shows the ferrous and nonferrous metals movement on the SHFE and DCE on 07 Sep , 2026
8 hours ago
JCC Hongyuan Copper's $200M Expansion Project Aims to Boost Capacity to 550,000 mt by 2027
8 hours ago
JCC Hongyuan Copper's $200M Expansion Project Aims to Boost Capacity to 550,000 mt by 2027
Read More
JCC Hongyuan Copper's $200M Expansion Project Aims to Boost Capacity to 550,000 mt by 2027
JCC Hongyuan Copper's $200M Expansion Project Aims to Boost Capacity to 550,000 mt by 2027
The 300,000 mt/year copper cathode expansion project of JCC Hongyuan Copper, a subsidiary of Jiangxi Copper Corporation, entered the pre-approval public notice stage of its environmental impact assessment on September 4, with a total investment of approximately 1.416 billion yuan. The project is planned to start construction in September 2026 and be completed in December 2027. Upon completion, JCC Hongyuan's total capacity will jump from 250,000 mt to 550,000 mt.
8 hours ago