MMG’s Kinsevere Produces 33,800 Tonnes of Copper Cathodes in First Half of 2026
MMG’s Kinsevere operation in the Democratic Republic of Congo produced 33,800 tonnes of copper cathodes in the first half of 2026, up 33% year on year, as the continued ramp-up of the Kinsevere Expansion Project and its sulphide processing facilities supported higher output.
Copper cathode production reached 16,820 tonnes in Q1, up 44% year on year, followed by 16,980 tonnes in Q2, up 24% from the same period of 2025. The improvement reflects the progressive ramp-up of Kinsevere’s sulphide processing circuit, including the concentrator and Roaster, Gas Cleaning and Acid Plant, together with increased contribution from the Nambulwa satellite pit.
Kinsevere remains on track to produce 65,000–75,000 tonnes of copper in 2026. At the midpoint of the guidance range, the mine would produce around 70,000 tonnes this year, meaning first-half output of 33,800 tonnes represents close to half of the implied annual target as the expanded operation continues to ramp up.
Power reliability, however, remains an operational constraint. MMG is developing a Battery Energy Storage System (BESS) to provide backup during temporary outages and improve power stability at Kinsevere. The investment highlights the importance of electricity reliability to sustaining higher utilisation rates as the expanded sulphide facilities move toward more stable production.
From a copper-market perspective, Kinsevere’s H1 performance shows that additional DRC supply is beginning to emerge not only from new mines but also from brownfield expansions and the conversion of existing operations toward sulphide resources. If Kinsevere reaches the upper end of its 2026 guidance, annual copper production would approach 75,000 tonnes, reinforcing the DRC’s growing contribution to global refined copper supply.