[SMM Flash] Brazil’s Bandeira Lithium Project Initiates Long-Lead Equipment Procurement

Published: Jun 12, 2026 09:47

On June 11, Lithium Ionic announced that it has placed the first long-lead equipment order for its Bandeira lithium project, located in the Lithium Valley region of Minas Gerais, Brazil. The order covers a 138/13.8 kV main power transformer for the project’s internal substation. The equipment will be supplied by Brazilian manufacturer Blutrafos.

According to the company, the transformer is a critical-path item that must be secured in advance of construction. The order marks the formal commencement of long-lead equipment procurement and indicates that the Bandeira project is gradually progressing from the engineering phase toward construction readiness.

Lithium Ionic stated that overall engineering progress at Bandeira has reached approximately 65%. To support detailed engineering and construction planning, the company has completed 1,352 metres of geotechnical drilling across the project area. The capital expenditure estimate is also being updated based on the latest engineering work, while additional long-lead equipment packages are expected to move forward through tendering and procurement.

The Bandeira project is 100% owned by Lithium Ionic and is located in Minas Gerais, one of Brazil’s key lithium-producing regions.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
[SMM Analysis] Portugal Cancels Construction of Integrated Lithium Mining and Processing Industry
9 hours ago
[SMM Analysis] Portugal Cancels Construction of Integrated Lithium Mining and Processing Industry
Read More
[SMM Analysis] Portugal Cancels Construction of Integrated Lithium Mining and Processing Industry
[SMM Analysis] Portugal Cancels Construction of Integrated Lithium Mining and Processing Industry
9 hours ago
[SMM Flash] SADC Urged to Shift from Raw Mineral Exports to Processing, Zimbabwe's Lithium Ban Cited as Model
14 hours ago
[SMM Flash] SADC Urged to Shift from Raw Mineral Exports to Processing, Zimbabwe's Lithium Ban Cited as Model
Read More
[SMM Flash] SADC Urged to Shift from Raw Mineral Exports to Processing, Zimbabwe's Lithium Ban Cited as Model
[SMM Flash] SADC Urged to Shift from Raw Mineral Exports to Processing, Zimbabwe's Lithium Ban Cited as Model
UN Economic Commission for Africa executive secretary Claver Gatete has called on the Southern African Development Community (SADC) to move from raw mineral exports toward local processing and value addition, calling the region a testing ground for Africa's broader mineral strategy. Demand for critical energy transition minerals including lithium could more than triple by 2030 under net-zero scenarios, with Africa holding about 30% of global reserves but just 1% of lithium output, the smallest share among minerals cited. Zimbabwe was named SADC's primary lithium resource holder, alongside the DRC (cobalt), South Africa (platinum, manganese) and Zambia (copper), with Gatete pointing to Zimbabwe's unprocessed lithium export ban as a policy model for the region. Minerals contribute about 10% of SADC's GDP, 25% of exports and 20% of government revenues, but only 7% of direct employment. SMM View: Gatete's remarks lend regional policy weight to Zimbabwe's ongoing beneficiation push, reinforcing the rationale behind its concentrate export ban as domestic sulfate capacity comes online.
14 hours ago
Sinomine's Bikita Lithium Sulfate Plant Begins Construction, Targets 2027 Completion Amid Zimbabwe's Export Ban Push
15 hours ago
Sinomine's Bikita Lithium Sulfate Plant Begins Construction, Targets 2027 Completion Amid Zimbabwe's Export Ban Push
Read More
Sinomine's Bikita Lithium Sulfate Plant Begins Construction, Targets 2027 Completion Amid Zimbabwe's Export Ban Push
Sinomine's Bikita Lithium Sulfate Plant Begins Construction, Targets 2027 Completion Amid Zimbabwe's Export Ban Push
Sinomine Resource Group's Zimbabwe unit, Masingo Lithium Technology, has obtained EIA approval for its 100,000 t/y lithium sulfate plant at Bikita, moving the project into full construction with contractors China Railway No. 9 Group and Shandong Dadi now on site. Completion is targeted for mid-2027. The clearance formalizes a plan first disclosed in September 2024 and reaffirmed via Sinomine's RMB 5.2 billion ($764 million) fundraising in May 2026, rather than signaling new capital commitment. Bikita becomes Zimbabwe's third Chinese-backed lithium sulfate project, joining Huayou's 50,000 t/y Arcadia plant commissioned July 2026, running near 60% of capacity as of late July and Yahua's Kamativi facility construction started February 2026, capacity undisclosed. Combined announced capacity across all three approaches 200,000+ t/y once complete, ahead of Zimbabwe's January 2027 concentrate export ban. SMM View: Arcadia's slower than nameplate ramp is the key benchmark here if Bikita follows a similar curve at double the capacity, full-rate output likely slips into 2028 despite a mid-2027 completion date. With all three plants now past groundbreaking, Zimbabwe's beneficiation push has shifted from policy to physical build out, the next signal to watch is how strictly the export ban is enforced against each plant's actual commissioning timeline, not just its announced one.
15 hours ago