CHN Energy has fully commissioned its 4 GW Lingwu PV project in Ningxia, following the grid connection of its Phase II 2 GW section. Part of a massive 6 GW mining-subsidence base, the site will deliver 10.8 TWh annually to the east via the 800 kV Ningxia-Zhejiang UHVDC line.
The project pioneers a 'solar-coal-storage-hydrogen' model, bundling PV with existing thermal assets and a 400 MW/800 MWh grid-forming storage system to smooth variability. By repurposing degraded coal lands, integrating 'PV + ecology' for vegetation recovery, and sharing an existing 750 kV coal plant substation, the base sets a benchmark for land reuse and long-distance clean energy transmission in western China.