[SMM Analysis] Rio Tinto Targets 200,000 tpy LCE Production by 2028

Published: Feb 28, 2026 15:49

This month, Rio Tinto stated during its earnings conference call that with all its owned projects progressing as planned, the company's lithium production capacity is expected to reach 200,000 metric tons of lithium carbonate equivalent (LCE) annually by 2028. The increase will primarily stem from the Fenix project, the expansion of Sal de Vida, and the commissioning of the Rincon and Nemaska projects. By that time, total output will exceed three times the 57,000 metric tons of lithium carbonate production achieved in 2025.

Rio Tinto previously announced its entry into the ranks of major lithium producers upon acquiring Arcadium, with plans to increase capacity to over 200,000 metric tons of lithium carbonate equivalent (LCE) annually by 2028. The company has now confirmed its focus on achieving this target, positioning lithium as a “significant” component within its business structure.

Expansion Projects:

The mechanical portion of the 10,000-ton-per-year expansion at Fenix, one of the Argentine salt lake projects, has been completed, with commissioning progress reaching 60%. The mechanical vapor recompression unit has been put into operation to support the planned first production run. The first production from the expanded capacity remains on track to commence in the second half of 2026.

At the new Sal de Vida project in Argentina, with an annual capacity of 15,000 metric tons, the mechanical works have been completed and commissioning is 40% complete. Production is expected to commence in the second half of 2026, projected to increase Rio Tinto's lithium output to 61,000–64,000 metric tons LCE in 2026.

Regarding future projects:

The Rincon project in Argentina, with an annual capacity of 60,000 metric tons, is progressing smoothly with its initial 3,000-metric-ton-per-year plant. It is expected to reach full capacity by year-end. The 57,000-metric-ton expansion plant has completed commissioning and is currently being started up, with first production planned for 2028. It will reach full production after a three-year ramp-up period. The mine has an estimated 40-year lifespan, with operating costs positioned in the top quartile of the industry cost curve.

The Nemaska project in Canada features an integrated lithium hydroxide production line with a designed capacity of 28,000 metric tons per year. The mine's engineering design is complete, with construction progress at 60%. The lithium hydroxide refinery is scheduled to commence commissioning in 2026 and achieve first production in 2028. For the Whabouchi and Galaxy mines, strategic business and capital discipline reviews are underway with Canadian partners to determine the development of one of these mines. A decision is expected in the first half of 2026 to secure an integrated spodumene supply solution for the lithium hydroxide plant by 2028.

In Chile, Rio Tinto anticipates closing agreements signed with state-owned mining companies Codelco and Enami in the first half of 2026. Rio Tinto has been selected as the private partner to develop Chile's two largest undeveloped lithium resources, with projects advancing upon agreement completion.

 

 

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
[SMM Flash] Fire Incident at Greenbushes CGP3; CGP1 and CGP2 Unaffected, FY2026 Production Guidance Maintained
37 mins ago
[SMM Flash] Fire Incident at Greenbushes CGP3; CGP1 and CGP2 Unaffected, FY2026 Production Guidance Maintained
Read More
[SMM Flash] Fire Incident at Greenbushes CGP3; CGP1 and CGP2 Unaffected, FY2026 Production Guidance Maintained
[SMM Flash] Fire Incident at Greenbushes CGP3; CGP1 and CGP2 Unaffected, FY2026 Production Guidance Maintained
On June 10, IGO Limited announced that a fire occurred on June 9 at Chemical Grade Plant 3 (CGP3) at the Greenbushes lithium operation. The fire has been extinguished and no injuries were reported. Talison Lithium has commenced a full investigation into the cause of the incident and the extent of the damage. The company will also assess the potential impact and required repairs. According to IGO, operations at Chemical Grade Plant 1 (CGP1) and Chemical Grade Plant 2 (CGP2) remain unaffected. Greenbushes production is still on track to meet IGO’s FY2026 spodumene concentrate guidance of 1.375–1.425 million tonnes. Greenbushes is one of the world’s most important low-cost sources of spodumene concentrate, while CGP3 is an important part of the mine’s incremental chemical-grade concentrate capacity. As CGP1 and CGP2 remain unaffected and IGO has not revised its FY2026 production guidance, the short-term impact on actual global spodumene supply is expected to be limited. However, the extent of the damage, the repair timeline and the recovery schedule for CGP3 should be monitored closely. If the incident materially delays the ramp-up of CGP3, it could affect the pace of Greenbushes’ future supply growth and marginal
37 mins ago
[SMM Hydrogen Cost] 20260610
1 hour ago
[SMM Hydrogen Cost] 20260610
Read More
[SMM Hydrogen Cost] 20260610
[SMM Hydrogen Cost] 20260610
1 hour ago
Hualing Cable: Recently Won Contract Amount of Approximately 531 Million Yuan
16 hours ago
Hualing Cable: Recently Won Contract Amount of Approximately 531 Million Yuan
Read More
Hualing Cable: Recently Won Contract Amount of Approximately 531 Million Yuan
Hualing Cable: Recently Won Contract Amount of Approximately 531 Million Yuan
16 hours ago
[SMM Analysis] Rio Tinto Targets 200,000 tpy LCE Production by 2028 - Shanghai Metals Market (SMM)