[SMM Analysis] This Week in the Hydrometallurgy Recycling Market: Ternary Black Mass Prices Held Steady, While LFP Black Mass Prices Fluctuated (2025.12.29-2025.12.31)

Published: Dec 31, 2025 18:38
This week, cobalt sulphate and nickel sulphate prices began to rise, while lithium carbonate prices fluctuated.

SMM December 31:

 

This week, cobalt sulphate and nickel sulphate prices started to rise, while lithium carbonate prices fluctuated.

 

Recently, spot and futures prices for lithium carbonate fluctuated, and the beginning of the week also fell within the period for just-in-time procurement before the month-end and the Chinese New Year. LFP black mass prices per % lithium fluctuated with lithium chemicals this week. However, upstream grinding enterprises, after observing lithium carbonate supply-demand and policies, were relatively optimistic about future prices. Prices also adjusted with futures, showing a strong increase. Taking LFP pole piece black mass as an example, the current price is 4,700-5,000 yuan/mtu, up WoW. Taking ternary black mass as another example: the current nickel and cobalt payables for ternary pole piece black mass are 76.5-78.5%, up 0.5% WoW, while lithium payables are 74-77%, basically flat MoM. The main reasons were that cobalt sulphate and nickel sulphate prices continued to rise this week, and LCO black mass supply was relatively limited. Currently, most enterprises have relatively limited cobalt inventory, and after clearing out old stock, they had to purchase new material from smelters. Currently, producing cobalt-based products from recycled black mass offers some profit, so multiple enterprises switched production lines in H2, leading to a further tightening of pure cobalt black mass supply and pushing prices higher. The price increases for salt products gradually transmitted costs to the ternary and LCO sectors, driving up the payables and prices for both ternary and LCO black mass.

 

 

 

SMM New Energy Research Team

Wang Cong 021-51666838

Ma Rui 021-51595780

Feng Disheng 021-51666714

Lu Yanlin 021-20707875

Zhou Zhicheng 021-51666711

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
20 hours ago
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
20 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
20 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
20 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
20 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.