Recently, the Shanxi Energy Bureau issued a notice on strengthening the management of new energy storage projects. The notice specifies that projects included in the reserve database must commence substantial construction within six months and achieve grid connection within 12 months. Additionally, these projects are prohibited from unauthorized transfer during the construction period and for five years after full-capacity grid connection.