Vedanta sees Aluminium costs falling below $1,700/t in H2FY26 as Sijimali bauxite mine nears approval

Published: Aug 4, 2025 20:46
Source: SMM
Source: Vedanta Limited FY 2026 Q1 earnings call, 31 July 2025

Vedanta Ltd told investors last week that it expects the cash cost of producing primary aluminium to slide beneath US $1,700 per tonne in the second half of FY 2026, supported by higher captive alumina output from its Lanjigarh refinery and the impending start-up of the Sijimali bauxite mine in Odisha.

“With Train II at Lanjigarh fully ramping and Sijimali contributing up to 1.5 million tonnes of bauxite, we are set for sub-$1,700 hot-metal costs,” Chief Operating Officer Anup Agarwal said on the company’s Q1 earnings call.

Bauxite: Sijimali heads for Q4 start

The Forest Advisory Committee signed off Sijimali’s first-stage clearance (FC-1) on 30 July. Management expects to complete the FC-2 and environmental (EC) approvals “within three to four months,” paving the way for mining to begin by the end of Q4 2026. The pit should supply 1.0–1.5 Mt of ore this year.

Exports from Emirates Global Aluminium’s Guinea unit remain suspended, but the company said the gap has been covered by other contracts. For the full year, Vedanta has already locked in the ~9 Mt of bauxite it needs to feed its alumina refineries:

Source

Volume (Mt)

Odisha Mining Corp. & other domestic mines

~5.0

Imports

~2.5

Sijimali (Odisha)

1.0–1.5

Alumina: Train II lifts captive mix to 65-70 %

Lanjigarh produced 584 kt of alumina in Q1 FY26 and remains on track for 3.0–3.1 Mt this fiscal year. The full ramp-up of Train II will lift Vedanta’s captive-alumina share from roughly 50 % to 65-70 %, pushing refinery cash costs below US $800 /t. Together with softer third-party alumina prices, management expects an additional US $80–100 /t savings over the next two quarters.

The plant currently operates at about 3.5 Mt /y. Management’s first milestone is to stabilise output at 5 Mt /y; once that level is reached, an 18-month debottlenecking campaign—focused on upgrading kilns, calciners, material-handling systems and outbound logistics (rail, port and other evacuation links)—will raise nameplate capacity to 6 Mt /y. The company still targets mechanical completion for this second-phase upgrade in the back half of FY27.

Primary aluminium: cost floor and capacity creep

Vedanta’s Q1 hot-metal cash cost fell 12 % quarter-on-quarter to US $1,765 /t on cheaper alumina and a higher captive mix. While planned maintenance at the Jharsuguda power plant will curb further gains in Q2, the company reaffirmed its full-year guidance of US $1,700–1,750 /t, aiming for the lower end in H2. Power costs are already “close to US $500 /t,” COO Anup Agarwal noted.

On the capacity side, the group is installing magnetic compensation loops in potlines at Jharsuguda and BALCO—a technology that boosts current efficiency and metal throughput. The retrofit underpins Vedanta’s plan to lift smelter capacity to 2.8–2.85 Mt within the next 18 months. And the target production for FY26 is 2.5-2.6 Mt.

Additionally, the company confirmed that the commissioning of the expansion of 435,000 tons per annum Balco smelter is targeted in the current quarter.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Metro Mining Resumes Bauxite Hills Operations Post-Cyclone, Targets 6.6-7.1M WMT in 2026
14 hours ago
Metro Mining Resumes Bauxite Hills Operations Post-Cyclone, Targets 6.6-7.1M WMT in 2026
Read More
Metro Mining Resumes Bauxite Hills Operations Post-Cyclone, Targets 6.6-7.1M WMT in 2026
Metro Mining Resumes Bauxite Hills Operations Post-Cyclone, Targets 6.6-7.1M WMT in 2026
[SMM Aluminum Express News] Metro Mining (ASX:MMI) resumed operations at Bauxite Hills in mid-March after Tropical Cyclone Narelle caused minimal disruption, with only seven days of lost production and no infrastructure damage. The Port of Skardon reopened on 25 March, with barging gradually returning to full capacity by mid-April. Despite the disruption, 100,000 WMT was shipped in March. Transhipping continues via TSA Skardon Floating Crane and ultramax vessels, while the Ikamba Offshore Floating Terminal is en route back from maintenance in Batam and expected to arrive end-April. Full-year 2026 shipments are forecast at 6.6–7.1 million WMT.
14 hours ago
SHFE Cast Aluminum Alloy Warrants Drop to 31,183 mt on April 7
14 hours ago
SHFE Cast Aluminum Alloy Warrants Drop to 31,183 mt on April 7
Read More
SHFE Cast Aluminum Alloy Warrants Drop to 31,183 mt on April 7
SHFE Cast Aluminum Alloy Warrants Drop to 31,183 mt on April 7
[SMM Express] SHFE data showed that on April 7, the total registered cast aluminum alloy warrants stood at 31,183 mt, a decrease of 453 mt from the previous trading day. Specifically, the total registered volume in Shanghai was 1,912 mt (down 30 mt), Guangdong 12,358 mt (down 121 mt), Jiangsu 3,602 mt (down 30 mt), Zhejiang 8,471 mt (down 272 mt), Chongqing 3,634 mt (unchanged), and Sichuan 1,206 mt (unchanged).
14 hours ago
Data: SHFE, DCE market movement (Apr 07)
16 hours ago
Data: SHFE, DCE market movement (Apr 07)
Read More
Data: SHFE, DCE market movement (Apr 07)
Data: SHFE, DCE market movement (Apr 07)
The following table shows the ferrous and nonferrous metals movement on the SHFE and DCE on 07 Apr , 2026
16 hours ago