On July 22, Dingsheng New Energy Materials issued an announcement stating that the construction period for some of its fund-raising investment projects had been extended. Specifically, the completion date for the project with an annual output of 800,000 mt of battery foil and supporting blank materials had been postponed from the originally scheduled August 2025 to December 2027.
The main reason for the extension was that the company terminated its 2022 private placement project on December 8, 2023, which led to changes in the overall funding arrangements for the project and consequently slowed down the construction progress.