Competition intensifies in the new energy and ESS power supply industry; Taijia Stock suspends construction of a 240 million yuan fundraising and investment project

Published: Jul 16, 2025 17:13
On the evening of July 15, Taijia Co., Ltd. (002843) announced that, based on the external environment and the company's actual situation, it would postpone the implementation of the "Cemented Carbide Band Saw Blade Production Line Construction Project" (with a planned investment of 112.1113 million yuan), the "High-Speed Steel Bimetal Band Saw Blade Production Line Construction Project" (with a planned investment of 122.805 million yuan), and the "New Energy Power Supply and ESS Production Site Project" (with a planned investment of 241.8379 million yuan). The dates for these projects to reach their predetermined usable states have all been postponed to September 20, 2026.

On the evening of July 15, Taijia Co., Ltd. (002843) announced that it would postpone the implementation of the "Carbide Alloy Band Saw Blade Production Line Construction Project" (with a planned investment of 112.1113 million yuan), the "High-Speed Steel Bimetal Band Saw Blade Production Line Construction Project" (with a planned investment of 122.805 million yuan), and the "New Energy Power Supply and Energy Storage Power Supply Production Base Project" (with a planned investment of 241.8379 million yuan) based on the external environment and the company's actual situation. The dates for these projects to reach their intended operational states have all been postponed to September 20, 2026.

Regarding the "New Energy Power Supply and Energy Storage Power Supply Production Base Project," Taijia Co., Ltd. stated that the project mainly produces optimizers, inverters, and Power Conversion Systems (PCS), among other products. In recent years, the market competition in China's new energy power supply and energy storage power supply industries has continued to intensify. Additionally, policy adjustments in the traditional European and American export markets for PV inverters have led to significant fluctuations in market demand. Based on a prudent assessment of the macroeconomic and industry situation, and to protect the interests of all shareholders and the company, Taijia Co., Ltd. has temporarily suspended the construction of the "New Energy Power Supply and Energy Storage Power Supply Production Base Project," which cannot be completed within the originally planned timeframe.

泰嘉股份相关募投项目

Relevant fund-raising projects of Taijia Co., Ltd.

To ensure the steady implementation of Taijia Co., Ltd.'s relevant fund-raising projects, reduce the risks associated with the use of raised funds, and considering the company's strategic planning, after careful deliberation, the company has decided to postpone the date for the "New Energy Power Supply and Energy Storage Power Supply Production Base Project" to reach its intended operational state to September 20, 2026.

According to available information, Taijia Co., Ltd. has been deeply involved in the sawing industry for over 20 years, with its products primarily consisting of bimetal band saw blades, including high-speed steel band saw blades and carbide alloy band saw blades. By the end of September 2022, the company entered the consumer electronics power supply business through mergers and acquisitions and rapidly expanded into the large power supply business, including new businesses and product categories such as new energy intelligent PV/energy storage power supplies, data center power supplies, and site energy power supplies.

It is reported that Taijia Co., Ltd.'s consumer electronics power supply business mainly includes power supplies for charging smart terminal products such as mobile phones, laptops, smart wearable devices, and smart home appliances, such as mobile phone chargers and adapters. The new energy intelligent PV/energy storage power supply business mainly includes products such as PV optimizers, PV inverters, and PCS. The data center power supply business mainly involves server power module products. The site energy business mainly involves household DC charging piles and fast charging power module products.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
19 hours ago
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
19 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
19 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
19 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
19 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.
19 hours ago