[Grid Connection of 100MW/200MWh ESS Power Station Project in Binhai New Area, Hai'an City, Jiangsu Province] Recently, the 100,000 kW/200,000 kWh ESS power station project in Binhai New Area, Hai'an City, Jiangsu Province, successfully completed grid connection and started operation. The project is located in Binhai New Area, Hai'an City, covering an area of approximately 31.73 mu. With a total investment of about 195 million yuan, the project includes an LFP ESS capacity of 115.345 MW/230.69 MWh, one 110 kV booster station, and is connected to the 110 kV voltage level power grid. After the project is put into operation, the annual average power generation is about 82.7 million kWh, providing a peak shaving capacity of 200 MWh for the Nantong region.