Luzhong Mining exceeded the target in the exploration tunnel project
iconJul 3, 2025 08:42
Source:SMM
[Luzhong Mining Completes Key Project of -500m Horizontal Exploration Tunnel] Recently, good news came from the mining preparation workshop. After the joint efforts of the construction personnel, the key project of the exploration tunnel in the Zhang mine area at the -500m horizontal level was overfulfilled. Originally planned to excavate 40 meters, the tunnel ultimately reached 63.4 meters, with a completion rate of 158.5%, laying a solid foundation for the company's deep resource exploration and subsequent mining planning with remarkable achievements.

For queries, please contact Lemon Zhao at lemonzhao@smm.cn