Shandong Keyu Energy Co., Ltd. is currently constructing a project with an annual production capacity of 300,000 mt of prebaked anode, with a total investment of approximately 1.1 billion yuan and a total land area of about 100 mu. In terms of on-site construction, experimental work and the foundation construction of the substation have been completed. It is expected that the main structure construction and equipment installation will be completed by the end of November this year, and trial production is planned to commence in December. After the project is fully operational, it is expected to achieve an annual production capacity of 300,000 mt of prebaked anode blocks.