The western section of the Kakula mine is expected to resume production by month-end

Published: Jun 3, 2025 18:38
According to Ivanhoe Mines: On June 3, Ivanhoe Mines announced that following the suspension of underground mining operations at the Kakula mine on May 20, 2025, senior management continues to work closely with a team of world-class geotechnical experts to safely and prudently resume mining operations. The engineering team at Kamoa Copper is updating the short-term, medium-term, and long-term plans for resuming operations in the eastern and western zones of the Kakula mine. It is expected that underground mining operations in the western zone of the Kakula mine will resume in late June, subject to the progress of dewatering efforts. The western zone of the Kakula mine has not been flooded and has a dewatering capacity of 1,000 liters per second.

According to Ivanhoe Mines: Kolwezi, Democratic Republic of the Congo (DRC) – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) announced on June 3 that following the suspension of underground mining operations at the Kakula Mine on May 20, 2025, senior management continues to work closely with a team of world-class geotechnical experts to safely and prudently resume mining operations.

(Image courtesy of Ivanhoe Mines)

The engineering team at Kamoa Copper is updating the short-, medium-, and long-term plans for resuming operations in the eastern and western sections of the Kakula Mine.Underground mining operations in the western section of the Kakula Mine are expected to resume in late June, subject to the progress of dewatering efforts. The western section of the Kakula Mine was not flooded and has a dewatering capacity of 1,000 litres per second.

It is anticipated that operations in the eastern section of the Kakula Mine will resume after the completion of dewatering efforts. Kamoa Copper has implemented a phased approach to dewater the entire Kakula Mine:

Phase 1: Install temporary dewatering equipment underground to maintain the current water level.Phase 1 was completed today, increasing the total dewatering capacity to approximately 4,400 litres per second, which is sufficient to manage the inflow of groundwater.

Phase 2: Install large power pumps and a permanent dewatering system that can be operated from the surface to conduct comprehensive dewatering operations across the entire Kakula Mine.Phase 2 has already commenced. Kamoa Copper has ordered four large power dewatering units, each with a dewatering capacity of 650 litres per second. Additional dewatering units will be ordered under the long-term infrastructure plan, which will be deployed in pairs and installed in existing ventilation shafts that extend deep into the catchment area of the Kakula Mine. The surface dewatering system is expected to be delivered and installed within 90 days.

Meanwhile, the Phase 1 and Phase 2 beneficiation plants continue to operate at approximately 50% of their combined capacity, processing ore from surface stockpiles.Once underground operations resume, ore from the western section of the Kakula Mine will be processed immediately.

Since mining commenced at the Kakula Mine in 2021, the mining team has completed more than 18 months of development ahead of schedule compared to the mining plan. This excess development has provided the underground mining team with significant flexibility to re-enter multiple mining areas once environmental safety is confirmed.

Mining activities at the Kamoa underground mine and the adjacent Phase 3 beneficiation plant continue to operate normally and have not been affected.

Ivanhoe Mines will announce the production resumption plan for the western section of the Kakula Mine and the restart plan for the eastern section next week.

Senior management of the Ivanhoe Mines and Kamoa Copper joint venture is working closely with a team of world-class geotechnical experts to conduct a comprehensive and prudent geotechnical evaluation of the Kakula Mine. It is expected to announce the evaluation results and the restart plan for the western and eastern zones of the Kakula mine next week.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
"Premier Li Qiang Leads State Council Meeting on Enhancing Effective Investment, Boosting Economic Growth"
13 hours ago
"Premier Li Qiang Leads State Council Meeting on Enhancing Effective Investment, Boosting Economic Growth"
Read More
"Premier Li Qiang Leads State Council Meeting on Enhancing Effective Investment, Boosting Economic Growth"
"Premier Li Qiang Leads State Council Meeting on Enhancing Effective Investment, Boosting Economic Growth"
Premier Li Qiang presided over an executive meeting of the State Council to study policy measures for promoting effective investment. The meeting noted that promoting effective investment plays an important role in stabilizing economic growth and strengthening momentum for development. It is necessary to innovate and improve policy measures, and intensify efforts to enhance the efficiency of utilizing funds such as central budget investments, ultra-long-term special treasury bonds, local government special bonds, and new-type policy-based financial instruments. In conjunction with formulating and implementing the 15th Five-Year Plan
13 hours ago
"Guided by Xi Jinping Thought, Implement 20th CPC Congress Spirit, Apply New Development Philosophy...
13 hours ago
"Guided by Xi Jinping Thought, Implement 20th CPC Congress Spirit, Apply New Development Philosophy...
Read More
"Guided by Xi Jinping Thought, Implement 20th CPC Congress Spirit, Apply New Development Philosophy...
"Guided by Xi Jinping Thought, Implement 20th CPC Congress Spirit, Apply New Development Philosophy...
Guided by Xi Jinping Thought on Socialism with Chinese Characteristics for a New Era, we will thoroughly implement the spirit of the 20th National Congress of the Communist Party of China and the plenary sessions of the Party’s 20th Central Committee, fully and faithfully apply the new development philosophy, strengthen top-level design, build computing power interconnection nodes oriented toward national hub periods, major strategic regions, and key industries, establish a system of computing power interconnection nodes, improve the efficiency and service level of public computing power resources, and promote high-quality development of computing power.
13 hours ago
Indirect Iran-US Nuclear Talks in Muscat Show Progress, Omani FM Mediates Tense but Efficient Discussions
13 hours ago
Indirect Iran-US Nuclear Talks in Muscat Show Progress, Omani FM Mediates Tense but Efficient Discussions
Read More
Indirect Iran-US Nuclear Talks in Muscat Show Progress, Omani FM Mediates Tense but Efficient Discussions
Indirect Iran-US Nuclear Talks in Muscat Show Progress, Omani FM Mediates Tense but Efficient Discussions
After intensive indirect consultations, the new round of nuclear talks between Iran and the US in Muscat, the capital of Oman, has achieved phased progress. It is reported that during this round of talks, the Iranian and US delegations did not meet directly. Instead, Omani Foreign Minister Badr acted as an intermediary, conveying a series of core proposals, strategic concerns, and policy positions to the other side. The atmosphere at the talks was tense yet efficient. According to preliminary on-site assessments, although both sides continue to negotiate over specific terms, they have reached a consensus on the key objective of "continuing dialogue."
13 hours ago