[Total Investment of 28 Billion Yuan! Inner Mongolia PV Project Plans to Be Fully Operational in Q4] The construction of JA Solar's low-carbon demonstration base project, which covers the entire industry chain and has a total investment of 28 billion yuan, is advancing at an "accelerated pace." "The 20GW monocrystalline wafer slicing workshop is currently undergoing pipeline installation, auxiliary equipment assembly, decoration, and other works. It is planned to start installing 192 monocrystalline furnace units on June 15, along with pouring wear-resistant floor concrete." "The main structure of the 10GW battery workshop has been completed, and work on floor casting, surrounding auxiliary facilities, and fire pipeline installation is underway. It is expected that the 5GW battery workshop will be handed over to the user on August 15, and the user will install battery process equipment." The project is expected to be fully operational in the fourth quarter of 2025.