[Phase I of the 200MW/200MWh Standalone ESS Project in Jinzhong, Shanxi, Connected to Grid and Put into Operation] On May 22, Phase I of the Yuangong 200MW/200MWh standalone ESS project (220kV Guiyuan ESS power station) in Jinzhong City, which was contracted and constructed by a certain Electric Power Co., Ltd., was successfully connected to the grid and put into operation. The project is located in Jinzhong Economic Development Zone, Shanxi Transformation and Comprehensive Reform Demonstration Zone, Jinzhong City, Shanxi Province. It is a standalone ESS project with a recorded installed capacity of 200MW/200MWh, constructed in two phases. The installed capacity of this phase is 100MW/100MWh.