Zhongpu Electromagnetic High-Efficiency Iron Core and Oriented Silicon Steel Processing Project Rushes Towards Production
Construction Scale and Content: The land area within the red line for the main part of the project is 17,169.80㎡. The project is planned to have a total construction area of 18,707.33㎡, including an above-ground total construction area of 8,410.38㎡ and an underground total construction area of 296.95㎡. The project's floor area ratio is 2.7, the building density is 61.53%, and the green space ratio is 5.06%. A new No. 1 workshop will be constructed, along with supporting outdoor works such as water supply and drainage, power supply and distribution, gas, green landscaping, and roads and sites. Upon completion, the project will have an annual processing capacity of 100,000 mt of oriented silicon steel and an annual production capacity of 45,000 mt of high-efficiency transformer iron cores.