Polaris Energy Storage Network News: On April 27, a tender announcement for the 246MW/492MWh distributed energy storage power station project in Jiangdu Economic Development Zone, Yangzhou, Jiangsu Province, was released. The documents indicate that the total investment for the project is approximately 590 million yuan, equivalent to a unit price of 1.199 yuan/Wh. The planned construction period is 365 calendar days, and joint bidding is not accepted.

Below is the original tender announcement:

Tender Announcement for the 246MW/492MWh Distributed Energy Storage Power Station Project in Jiangdu Economic Development Zone

I. Tender Conditions

This tender project, the "246MW/492MWh Distributed Energy Storage Power Station Project in Jiangdu Economic Development Zone," has been approved for construction. The bid inviter is "Yangzhou Jiangdu Jiangzhou Industrial Development Co., Ltd." The funding for the tender project is self-raised (source of funds), with a contribution ratio of 100%. Qualified bid applicants are now invited to participate in the project registration through public tender.

II. Project Overview

1. Project Location: Jiangdu Economic Development Zone, Yangzhou City.

2. Project Content and Scale: This project plans to utilize the existing sites of enterprises within the Jiangdu Economic Development Zone to construct an energy storage power station, with a planned installed capacity of 246MW/492MWh. The lithium iron phosphate (LFP) batteries for the energy storage power station will be arranged in fully prefabricated cabins, with 246 2MWh energy storage battery cabins placed outdoors. The energy storage battery cabins will adopt a 1MW/2MWh cabinet configuration scheme using LFP batteries. Each energy storage battery cabin will be equipped with one 1000kW Power Conversion System (PCS), and each set of energy storage battery cabins will be connected to one 1000kVA local step-up transformer. The PCS and 10kV local step-up transformers will be installed outdoors as complete integrated units.

3. Total Investment for This Project: Approximately 590 million yuan.

4. Planned Construction Period: 365 calendar days.

5. Project Standards: Qualified.

6. Quality Grade Requirements: Qualified.

III. Project Section Division and Tender Content

This tender does not divide the project into sections. The tender content is the construction of the 246MW/492MWh distributed energy storage power station project in Jiangdu Economic Development Zone.

IV. Registration Conditions

1. This tender requires that bidders have corresponding construction capabilities in terms of personnel, equipment, and funding, and meet the following requirements: (1) The ability to independently enter into contracts; (2) The enterprise's qualification category, grade, and the project leader's registered profession and qualification registration comply with relevant national regulations; (3) The enterprise meets safety production conditions and has obtained a safety production license issued by the construction administrative department.

2. The project leader proposed by the bidder must be registered with the bidder's unit and possess a valid safety production assessment certificate (B certificate), and meet the following conditions: (1) The project leader is not concurrently employed or practicing in two or more units; (2) The project leader has no ongoing projects (the project manager has no ongoing projects, and the bidder must provide a signed and stamped commitment letter); (3) The project leader has no record of bribery-related criminal activities, or if there is a record, it has been more than five years since the record date. (4) If, after winning the bid, the bid inviter finds through spot checks that the bid winner is inconsistent with the commitments made during bidding, the bid inviter may determine the second-ranked bid candidate as the bid winner. If the second-ranked bid candidate is disqualified for the same reasons specified in the preceding paragraph or declines to win the bid, the bid inviter may determine the third-ranked bid candidate as the bid winner, and so on.

3. Joint bidding is not accepted for this tender.

Original Title: 1.199 yuan/Wh! Tender for 246MW/492MWh Distributed Energy Storage Power Station in Jiangsu

For queries, please contact Lemon Zhao at lemonzhao@smm.cn

For more information on how to access our research reports, please email service.en@smm.cn

SMM Events & Webinars

All