[Gotion High-tech's Largest ESS Battery Production Site in Western China May Start Operation in October] The Gotion High-tech Western China New Energy Battery Intelligent Manufacturing Base project commenced construction in April this year. Currently, the foundation trenching for workshops No. 1 to No. 3 has been completed, and work is underway on foundation dynamic compaction, earthwork backfilling, and outdoor supporting facilities construction. It is expected that equipment will begin arriving at the site in July, and after completion of commissioning in October, the project will commence operation. It is reported that the project's products are 314Ah large-capacity prismatic LFP battery cells and their system integration products for the ESS sector. The products feature top-tier energy efficiency, leading intelligence, and in-house R&D across the entire industry chain. Upon commencement of operation, it is expected that 1,000 new jobs will be created. As Gotion High-tech's most intelligent production site in western China, with the largest scale, highest degree of automation, and most advanced products, the project will fill the gap in battery cell manufacturing by leading enterprises in the autonomous region.