590 Million Yuan! ESS Power Station Project in Yinchuan, Ningxia Tops Out. On March 25, the Jiyang Green Storage 200 MW/400 MWh Shared ESS Power Station Project, constructed by China Construction Third Engineering Bureau First Construction Engineering Co., Ltd., officially topped out. (Battery Network)

According to the media center of Xixia District, Yinchuan, Ningxia, on March 25, the Jiyang Green Storage 200 MW/400 MWh shared ESS power station project, undertaken by China Construction Third Engineering Bureau First Construction Project Co., Ltd., officially topped out.

"Currently, the project has successfully completed the construction and acceptance of the main structure according to the construction plan, and key equipment such as transformers, batteries, and liquid cooling systems have been scheduled for production. We plan to complete all battery installation and debugging in April and finish the grid connection acceptance in May," said Wang Sheng, project manager of Jiyang Green Storage at China Construction Third Engineering Bureau First Company.

It is understood that the project is located east of Wenchang South Street and south of the South Ring Expressway in Xixia District, with a total investment of 590 million yuan and a total area of approximately 55.4 acres. The rated installed capacity is 200 MW/400 MWh, focusing on the construction of an ESS power station, a comprehensive building, a transformer substation, a gatehouse, and a 220KV substation.