【SMM Analysis】Update on Mali's Bougouni Lithium Project: Steady Production Ramp-up and Orderly Mining License Transfer Progress

Published: Apr 11, 2025 14:40
The dense media separation (DMS) processing plant at the site has cumulatively produced over 11,000 tonnes of spodumene concentrate to date, demonstrating steady progress toward commercial production. During the final week of March 2025, the plant processed 13,400 tonnes of raw ore, yielding 1,920 tonnes of spodumene concentrate grading 5.63% Li₂O.

Kodal Minerals recently provided an update on the progress of its Bougouni Lithium Project located in southern Mali. Operated by its UK subsidiary KMUK, the project is nearing completion of construction and successfully produced its first batch of lithium spodumene concentrate in February 2025. The dense media separation (DMS) processing plant at the site has cumulatively produced over 11,000 tonnes of spodumene concentrate to date, demonstrating steady progress toward commercial production. During the final week of March 2025, the plant processed 13,400 tonnes of raw ore, yielding 1,920 tonnes of spodumene concentrate grading 5.63% Li₂O.

The project has already stockpiled spodumene concentrate equivalent to its expected first-month production volume, with inventory continuing to grow to ensure stable future supply. Once the Malian government completes the mining license transfer and issues export permits, the concentrate will be shipped to China via the Port of Abidjan in Côte d'Ivoire. Regarding the license transfer, the process to shift ownership from Future Minerals SARL to locally registered Les Mines de Lithium de Bougouni SA (LMLB) is advancing smoothly. The restructuring of LMLB's shareholding has received signed approvals from Mali's Ministers of Mines and Finance, with only the final endorsement from President Assimi Goïta remaining.

Due to delays in the license transfer process, KMUK has formally requested an extension for its second payment of $7.5 million to the Malian government as stipulated in the agreement. The government has acknowledged receipt of the request and is currently reviewing it. Bernard Aylward, CEO of Kodal Minerals, stated that ongoing optimization and modifications at the processing plant are delivering positive results, with production ramp-up proceeding as planned. The accumulating concentrate stockpile and increasing production capacity have laid a solid foundation for achieving the target output of 11,000 tonnes per month. The company is fully supporting KMUK to complete the license transfer and looks forward to the President's final approval marking the successful conclusion of this critical process.

As a strategically important lithium development project in West Africa, the successful commissioning of the Bougouni Lithium Mine will contribute positively to diversifying the global lithium supply chain. This case also highlights the crucial role of host country policies in mining development. As the project transitions into commercial production, it is poised to become a significant source of lithium supply for the global new energy industry.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
SPIC Launches Tender for Da'an Gaseous Hydrogen Storage EPC Project
34 mins ago
SPIC Launches Tender for Da'an Gaseous Hydrogen Storage EPC Project
Read More
SPIC Launches Tender for Da'an Gaseous Hydrogen Storage EPC Project
SPIC Launches Tender for Da'an Gaseous Hydrogen Storage EPC Project
[SMM Hydrogen Energy Bulletin] On March 10, SPIC issued a tender announcement for the EPC general contracting of the Da'an Gaseous Hydrogen Storage Technology Retrofit Project. The project was located in Da'an, Jilin, with Da'an Jidian Green Hydrogen Energy as the owner. It involved the construction of six 1,850 m³ hydrogen storage spherical tanks and one 8,000 Nm³/h compressor, with total hydrogen storage capacity of 177,600 Nm³. The construction period will run from May 1 to November 30, 2026, and consortium bids will not be accepted.
34 mins ago
Yalian Hydrogen Energy Secures Four New National Patents for Key Hydrogen Tech
44 mins ago
Yalian Hydrogen Energy Secures Four New National Patents for Key Hydrogen Tech
Read More
Yalian Hydrogen Energy Secures Four New National Patents for Key Hydrogen Tech
Yalian Hydrogen Energy Secures Four New National Patents for Key Hydrogen Tech
[SMM Hydrogen Energy News Flash] Following the acquisition of three patents earlier this month, Yalian Hydrogen Energy recently obtained another four nationally authorized patents: a hydrogen production reactor, a method for producing synthesis gas from semi coke coke oven coal gas, a hydrogen production system via water electrolysis powered by wind and solar power generation, and a horizontal gas processor for alkaline water electrolysis hydrogen production. These patents focus on key technological links in the hydrogen energy industry chain.
44 mins ago
Led by 9 Academicians! Detailed Agenda Released for the 9th Conference on Frontier Energy Storage Technologies
2 hours ago
Led by 9 Academicians! Detailed Agenda Released for the 9th Conference on Frontier Energy Storage Technologies
Read More
Led by 9 Academicians! Detailed Agenda Released for the 9th Conference on Frontier Energy Storage Technologies
Led by 9 Academicians! Detailed Agenda Released for the 9th Conference on Frontier Energy Storage Technologies
2 hours ago