Recently, the 500,000 kW desertification control and PV integrated project of CECEP Solar in Dalad Banner has fully resumed construction in the heart of the Kubuqi Desert. The project builders are seizing the golden period of spring construction, striving to achieve the goal of full-capacity grid connection by the end of June. The project is expected to complete the installation of solar panel mounting brackets by the end of April, and the installation of PV modules by the end of May. Simultaneously, the construction of the booster station, ESS power station, and transmission projects will be carried out to achieve grid-connected power generation by the end of June.