I. According to
the plan of Inner Mongolia Xingshun New Materials Co., Ltd. to construct the High-Efficiency and Energy-Saving High-Carbon Ferrochrome Alloy Project with an annual output of 528,000 mt, the unit responsible for preparing the Environmental Impact Report has been determined. In accordance with the Environmental Protection Law of the People's Republic of China, the Environmental Impact Assessment Law of the People's Republic of China, the Regulations on the Administration of Environmental Protection for Construction Projects, and the Measures for Public Participation in Environmental Impact Assessment (Ministry of Ecology and Environment Order No. 4), public opinions are now being solicited.
II. Basic Information of the Construction Project
1. Project Name: High-Efficiency and Energy-Saving High-Carbon Ferrochrome Alloy Project with an Annual Output of 528,000 mt by Inner Mongolia Xingshun New Materials Co., Ltd.;
2. Name of the Construction Unit: Inner Mongolia Xingshun New Materials Co., Ltd.;
3. Contact Information of the Construction Unit: Zengkang Chen, 15980194006;
4. Name of the Unit Preparing the Environmental Impact Report: Inner Mongolia Huatai Hanguang Environmental Technology Co., Ltd.;
5. Project Location: Shiguai Industrial Park, Baotou City, Inner Mongolia;
6. Project Content: Construction of 2×75,000 kVA fully enclosed AC submerged arc furnaces, 2×57,000 kVA fully enclosed AC submerged arc furnaces, and supporting chain grate-rotary kiln production lines, tail gas generator sets, and other related auxiliary facilities. Upon completion, the project will produce 528,000 mt of high-carbon ferrochrome annually.
III. Main Content of Public Opinion Solicitation
Public opinions and suggestions regarding the environmental impact of this project are being solicited. Please fill out the Public Opinion Form (link: https://pan.baidu.com/s/1XRrE6KMqYj3Tq1LdMDuJTA; access code: 8888). Opinions or demands unrelated to the environmental impact assessment of the construction project, such as those concerning land acquisition, property, or employment, do not fall within the scope of public participation in the environmental impact assessment. During the preparation of the draft Environmental Impact Report for public consultation, the public may submit opinions related to the environmental impact assessment to the construction unit.
IV. Methods and Channels for Submitting Public Opinions
The public may provide feedback to the construction unit via telephone, email, fax, or mail. When submitting opinions, the public should provide valid contact information.
Contact Person: Zengkang Chen
Mailing Address: Inner Mongolia Xingshun New Materials Co., Ltd.
Contact Number: 15980194006
V. Others
The construction unit will not use the personal information submitted by the public for purposes other than public participation in the environmental impact assessment, nor will it disclose such information without the consent of the relevant rights holders, except as otherwise provided by laws and regulations.
Inner Mongolia Xingshun New Materials Co., Ltd.
December 24, 2024