【SMM Analysis】NextEra Energy Resources Seeks State Approval for 1.2GWh BESS Amid City Moratorium

Published: Nov 22, 2024 19:13
【SMM Analysis】NextEra Energy Resources, a leading company in renewable energy and battery storage, is seeking approval from the California state regulator for a 1.2GWh Battery Energy Storage System (BESS) to bypass a city's moratorium on such projects.

NextEra Energy Resources, a leading company in renewable energy and battery storage, is seeking approval from the California state regulator for a 1.2GWh Battery Energy Storage System (BESS) to bypass a city's moratorium on such projects.

Project Overview

  1. North Central Valley Energy Center

    • Location: San Joaquin County, California
    • Capacity: 132 Megawatts
    • Features: The project spans approximately 60 acres and began commercial operation in November 2023. It uses batteries to store energy, improving the reliability and efficiency of the electric grid.
    • Community Benefits: The project is expected to bring economic opportunities while ensuring reliable access to energy and preserving clean air and water.
  2. Desert Peak Project

    • Location: Riverside County, California
    • Capacity: 400 Megawatts
    • Features: The project covers about 50 acres and is subject to local and state approvals. It is scheduled to begin operations in 2023.
    • Community Benefits: Similar to the North Central Valley project, this initiative aims to provide reliable energy access and significant economic benefits to the hosting community.
  3. Kola Project

    • Location: Alameda County, California
    • Capacity: 700 Megawatts (Kola I and Kola II combined)
    • Features: Kola I covers approximately 180 acres and is scheduled to begin operations in 2024. Details for Kola II are pending.
    • Community Benefits: The project is designed to enhance energy reliability and contribute to the local economy.

Regulatory Context and Moratorium Bypass

  • Corby Project

    • Location: Near the Vaca-Dixon Substation
    • Capacity: 300 Megawatts
    • Regulatory Action: NextEra has initiated the application process for approval through the state energy commission, circumventing local authorities. This move is in response to moratoriums placed by the City of Vacaville and Solano County.
    • Legal Basis: The 2022 bill AB 205 grants the California Energy Commission full authority over permitting, allowing projects to bypass local moratoriums.
  • Implications of AB 205

    • State vs. Local Control: AB 205 creates a state-level pathway for approval, removing local control over projects like the Corby Project. This has led to concerns about local autonomy and the ability of communities to regulate developments within their jurisdictions.
    • Developer Motivation: Developers like NextEra are motivated to seek state-level approval to avoid delays caused by local moratoriums, which can extend for years. This approach ensures that projects can proceed without waiting for local governments to lift restrictions.

Community and Environmental Considerations

  • Safety Concerns

    • Public workshops and meetings have been held to discuss the safety of BESS installations. Experts have assured that the technology is safe and vital for the clean energy future of the region and state.
    • Public Perception: Despite assurances, there is resistance from some locals due to concerns about the location of substations and the potential environmental impact of BESS facilities.
  • Economic Impact

    • Battery energy storage projects are expected to generate significant economic benefits for the communities that host them. This includes job creation and additional revenue for local communities.
    • Investment: NextEra has invested over $7.1 billion in California, including in wind, solar, and energy storage projects. These investments are part of a broader effort to fuel economic growth and move towards energy independence.

Conclusion

NextEra Energy Resources' move to seek state-level approval for its 1.2GWh BESS project highlights the ongoing tension between state and local control over energy infrastructure projects. While state regulations like AB 205 provide a pathway for developers to bypass local moratoriums, this approach raises questions about local autonomy and community involvement in decision-making processes. The projects promise significant economic and environmental benefits, but they also spark debates about safety, local control, and the future of energy infrastructure in California.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
11 hours ago
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
11 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
11 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
11 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
11 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.
11 hours ago