JISCO Group Dongxing Aluminum Launches Distributed PV Power Generation Project
게시됨: Nov 16, 2024 21:09
공유
공유
저장
On November 14, JISCO Group Dongxing Aluminum Jiayuguan Branch officially commenced the distributed photovoltaic power generation and new energy consumption project. Upon completion, the project will generate 56,798,600 kWh annually, save 17,000 mt of standard coal per year, and reduce carbon dioxide emissions by 47,000 mt annually. The project has an absolute construction period of six months and is undertaken by China Power Construction Group Shandong Electric Power Construction First Engineering Company as the EPC general contractor and construction builder. The project will utilize 682,800 m² of idle land around Dongxing Aluminum Company to install photovoltaic power generation units, which will be connected to the nearby 10 kW aluminum switch station for local consumption, with a total installed capacity of 36.5 MWp.