SMM has learned that on May 20, the Energy Bureau of Inner Mongolia Autonomous Region issued the "Special Action Plan for the Development of New Energy Storage in Inner Mongolia Autonomous Region 2024-2025." The document specifies that in 2024, 10GW of new energy storage will start construction, with 6.5GW/29GWh to be completed and put into operation; in 2025, another 11GW of new energy storage will start construction, with 14.5GW/65GWh to be completed and put into operation. The total planned construction scale for energy storage on the power generation side is 14GW/58GWh, to be connected to 12 500kV substations; the total planned construction scale for energy storage on the grid side is 7GW/36GWh, to be connected to 6 500kV substations.