[Lanzhou Baohang 100,000-ton negative electrode material project will be put into production] Baowu Carbon Industry Lanzhou Baohang 100,000-ton negative electrode material project is making full efforts to achieve the project completion goal. As of now, all roadways, landscaping, and external process pipelines in the plant area have been completed, and the civil and steel structure of Plant 1, Plant 2, and Plant 3 have been delivered, with the remaining items expected to be completed by the end of March. It is reported that the total investment of the Lanzhou Baohang 100,000-ton negative electrode material project is 4.1 billion yuan, with the first phase of 50,000 tons of negative electrode materials and 100,000 tons of graphite production lines and auxiliary facilities expected to be completed and put into operation in 2024, and the second phase planned to be completed and put into operation in 2026. After the project is fully completed and put into operation, it will have an annual production capacity of 100,000 tons of negative electrode materials.