[SMM Analysis] China's energy storage bid winning capacity declined slightly in January, stand-alone energy storage projects increased

Published: Feb 07, 2024 18:04 (GMT+8)
Source: SMM
[SMM Analysis: China's energy storage bid winning capacity declined slightly in January, stand-alone energy storage projects increased] According to SMM, based on the EPC/system bid winning results of energy storage projects tracked by SMM in January, the total capacity reached 1.6GW/3.0GWh. The capacity of bid wins in a single month declined compared to December. The largest bid winning volume this month came from...

Based on the EPC/system bid winning results of energy storage projects tracked by SMM in January, the total capacity reached 1.6GW/3.0GWh. The capacity of bid wins in a single month declined compared to December. The largest bid winning volume this month came from the EPC general contracting project for Phase I of the 100MW/200MWh Guanling Yueliangwan electrochemical energy storage power station, with the energy storage power station having a capacity of 100MW/200MWh. The planned site of the energy storage power station is 3.2km west of Guanling County, Anshun City, Guizhou Province. It is an electrochemical energy storage power station adopting lithium iron phosphate lithium batteries. The operation mode of the energy storage power station focuses on smoothing renewable energy power plant output and peak shaving, while taking into account a certain frequency regulation capability. In terms of prices, the average bid winning price of 2-hour energy storage systems was RMB 0.74/Wh, still at low levels; the average bid winning price of 2-hour energy storage EPC was RMB 1.22/Wh, with little change compared to December. Entering 2024 Q1, most energy storage projects are still in the demonstration phase, and bid winning capacity declined notably. It is worth mentioning that based on the project information tracked by SMM, the proportion of shared energy storage projects increased markedly. Currently, problems of low utilization

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
[Energy storage: Sungrow, CATL among five winners of CNNC 2.98GWh storage procurement]
Oct 16, 2026 14:03 (GMT+8)
[Energy storage: Sungrow, CATL among five winners of CNNC 2.98GWh storage procurement]
Read More
[Energy storage: Sungrow, CATL among five winners of CNNC 2.98GWh storage procurement]
[Energy storage: Sungrow, CATL among five winners of CNNC 2.98GWh storage procurement]
CNNC announced winners of its 2026-2028 LFP energy storage system centralized procurement on October 14. Sungrow, CATL, Zhongtian Energy Storage, CRRC Zhuzhou Institute and Kehua won with bids of RMB 0.4995-0.5329/Wh. The 2.98GWh tender attracted 33 bidders, covering 2-hour and 4-hour systems with a 1500V DC design and requirements for grid services such as primary frequency regulation and reactive power support.
Oct 16, 2026 14:03 (GMT+8)
[Energy storage: HiTHIUM cumulative shipments top 200GWh, Chongqing long-duration line supports delivery]
Oct 16, 2026 14:03 (GMT+8)
[Energy storage: HiTHIUM cumulative shipments top 200GWh, Chongqing long-duration line supports delivery]
Read More
[Energy storage: HiTHIUM cumulative shipments top 200GWh, Chongqing long-duration line supports delivery]
[Energy storage: HiTHIUM cumulative shipments top 200GWh, Chongqing long-duration line supports delivery]
HiTHIUM held a 200GWh shipment milestone ceremony in Chongqing on October 15, doubling from 100GWh in just over a year and rising to No.2 globally in 2025 from fifth in 2023. Its Chongqing plant runs the world's first dedicated long-duration storage cell line, rolling out 200 kAh-class cells per hour with over 89% automation, and was named a WEF Lighthouse Factory in January. Since settling in Tongliang, the company has drawn 18 upstream and downstream firms, generating RMB 10.85 billion in output in January-September, up 54% YoY.
Oct 16, 2026 14:03 (GMT+8)
[Energy storage: LONGi starts production at Suzhou base, grid-scale integration capacity targeted at 50GWh]
Oct 10, 2026 19:47 (GMT+8)
[Energy storage: LONGi starts production at Suzhou base, grid-scale integration capacity targeted at 50GWh]
Read More
[Energy storage: LONGi starts production at Suzhou base, grid-scale integration capacity targeted at 50GWh]
[Energy storage: LONGi starts production at Suzhou base, grid-scale integration capacity targeted at 50GWh]
LONGi's Suzhou base officially started production on Oct 9, covering containerized storage, C&I storage and control cabinets. Its grid-scale integration line will have 31GWh annualized capacity from October, expanding to 50GWh in 2027, plus over 10,000 C&I units per year by end-October. LONGi acquired control of Jingko Energy (about 62% voting rights) in Nov 2025; cumulative storage orders exceeded 3GWh in H1 2026, with a 6GWh shipment target for the full year.
Oct 10, 2026 19:47 (GMT+8)