SMM Analysis: Lithium Carbonate Futures Hit Daily Upside Limit after Persistent Slump, Potential Supply Changes Deserve Attention as Smelters Are Plagued by Severe Losses

Published: Dec 7, 2023 13:41
Lithium Carbonate futures fell 17 out of 18 trading days, hitting daily downside limits on Nov 22, Nov 27, Dec 5. Today, after frequent record lows, the most-traded contract surged by 6.99%, closing at 95,600 yuan/mt—a daily upside limit. Other contracts also hit the daily upside limit.

Lithium Carbonate futures fell 17 out of 18 trading days, hitting daily downside limits on Nov 22, Nov 27, Dec 5. Today, after frequent record lows, the most-traded contract surged by 6.99%, closing at 95,600 yuan/mt—a daily upside limit. Other contracts also hit the daily upside limit.
Regarding lithium carbonate's frequent past drops and today's sudden spike, the prior fall was largely due to bears at upper hand over bulls. Now, futures are re-aligning with spot prices, causing a notable rebound in lithium carbonate futures.
Per SMM, as of December 7, the spot price for domestic battery-grade lithium carbonate ranges between 115,000 and 126,000 yuan/mt, averaging 120,500 yuan/mt.
Despite lithium carbonate futures rebounding, market fundamentals remain unchanged with strong supply and weak demand. Lithium salt companies focus on bulk deliveries as individual order prices continue to drop. Some salt lake companies sell lithium carbonate at low prices.
Chile exported 13,592 mt of lithium carbonate to China in November, down 19.05% month-on-month, and up 35.04% year-on-year. Due to the long shipping time, there is a time lag between China’s imports of lithium carbonate from Chile and Chile’s exports of lithium carbonate to China. In October and November, Chile’s exports of lithium carbonate to China were 16,791 mt and 13,592 mt respectively. China’s imports of lithium carbonate averaged 12,137 mt per month from January to October. It is expected that China’s lithium carbonate imports will remain at a high level in November and December, which will increase supply in the domestic market.
SMM research reveals that due to weak end-user demand, cathode factories' orders dropped significantly. Amid price falls, cathode companies mostly adopted a wait-and-see approach, restocking sporadically at low prices. Some aim to deplete their raw material stocks by year's end, impeding short-term procurement demand. However, recent market research shows a shift in procurement sentiment among some downstream cathode companies, with occasional small purchases from traders at relatively low prices.

Meanwhile, the current drop in lithium carbonate prices pressures high-cost lithium salt businesses, with many upstream factories incurring losses. Market reports suggest a particular lithium salt firm had to reduce output due to continuous losses, future production plans now being driven solely by long-term sales volume.
Moreover, while some lithium salt firms that carried out maintenance in October won’t need immediate further maintenance, typically around February is their seasonal maintenance time. Some plan to halt production for January maintenance. Given the ongoing substantial losses from externally procured lithium ore, future maintenance and production plans of high-cost lithium salt companies dependent on externally sourced ore will notably affect domestic lithium carbonate supply dynamics.

Moving forward, monitoring high-cost lithium salt companies' production schedules amid sustained losses is crucial. SMM will continue tracking these developments. In the short term, the market's reception of major salt lake factories' shipments also warrants attention.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
11 hours ago
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Read More
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Recently, the official account of Shaanxi Construction No. 7 Construction Group announced that Phase I of the 200 MW/301.75 MWh hybrid frequency regulation ESS power station project in the Yuncheng Economic and Technological Development Zone, Shanxi, which it undertook, was successfully connected to the grid and officially entered the trial operation stage. The project mainly includes the construction of a 50 MW flywheel independent frequency regulation ESS, a 150 MW LFP electrochemical ESS, a 220 kV substation, and supporting facilities, adopting a hybrid model of “flywheel energy storage + LFP electrochemical energy storage.”
11 hours ago
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
11 hours ago
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
Read More
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
Recently, the PV+ESS integration project of Xuzhou Sinoma Cement Co., Ltd., invested in and built by Sinoma Overseas, successfully achieved a breakthrough at a key period and was officially energized and put into operation on March 16, 2026, marking the formal commissioning of this regional integrated demonstration project for “hybrid energy storage + PV.” The project deeply integrated PV power generation and hybrid energy storage technologies to establish a clean energy supply system featuring “self-generation for self-use, flexible regulation, safety, and high efficiency.” The project’s total ESS installations capacity reached 10 MW/20 MWh, with total PV capacity of 11.38 MW, forming a complete green energy chain of “PV power generation + hybrid energy storage,” providing continuous and stable power support for production processes, building a closed-loop smart energy system with deep integration across the power generation side, energy storage side, and power consumption side, and realizing intelligent coordination and optimized operation throughout the entire life cycle of energy production, storage, consumption, and regulation.
11 hours ago
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
11 hours ago
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
Read More
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
Recently, the Shijiazhuang Gaoyi County 300 MW/600 MWh shared ESS power station, a key new-type energy storage project in Hebei province, officially completed the full-capacity delivery of its ESS, marking this regional benchmark energy storage project’s entry into the critical stage before production and operation. The successful delivery of the Gaoyi County 300 MW/600 MWh shared ESS power station represents another landmark implementation of Zhiguang Energy Storage’s core technologies in large-scale shared energy storage projects in north China, further consolidating Zhiguang Energy Storage’s industry-leading position in the field of cascaded high-voltage, large-capacity energy storage.
11 hours ago