SHANGHAI, Mar 21 (SMM) – The table below shows the capacity expansion plans of LiPF6 companies in China in February.
|
LiPF6 companies |
Headquarters location |
Installed capacity (10,000 mt) |
Expansion plans |
|
Jiangsu Jiujiujiu Technology |
Jiangsu |
0.5 |
•It announced 35,000 mt/year lithium hexafluorophosphate project and 10,000 mt/year sodium hexafluorophosphate project, of which the first phase with an annual output of 18,000 mt of lithium hexafluorophosphate is expected to be completed in 2025. |
|
DFD |
Henan |
5.5 |
•The 20,000 mt/year high-purity crystalline lithium hexafluorophosphate project of DFD Yangfu New Materials is now under environmental impact assessment, with an annual capacity of 100,000 mt in the first phase. |
|
Baoni New Material |
Shandong |
0 |
•It announced 100,000 mt/year of liquid lithium salt project, 60,000 mt/year of lithium hexafluorophosphate project, and 50,000 mt/year of lithium bisfluorosulfonyl imide project, all of which are now under environmental impact assessment. Among them, Phase I 5,000 mt/year lithium hexafluorophosphate, 1,000 mt/year lithium bisfluorosulfonyl imide, and 100,000 mt/year liquid lithium salt are scheduled to start construction in July this year. |
![[SMM Revisión semanal del mercado de celdas de baterías de almacenamiento de energía 9.3] La escasez de láminas de cobre limita los programas de producción de septiembre, los precios de las celdas de baterías de almacenamiento de energía se mantienen firmes](https://imgqn.smm.cn/usercenter/tKgKv20251217171725.png)