Second fire! Accidents continue to occur at the largest energy storage battery power station in the world!

Published: Feb 20, 2022 09:47
The second fire! Accidents continue to occur at the largest energy storage battery power station in the world! For a long time, people familiar with lithium batteries can't help thinking of battery supplier LG New Energy when they see a fire in an energy storage project. Yes, this time it also has something to do with LG new energy. According to media reports, on the evening of February 13, 2022, an accident occurred at the Moss Landing energy storage power plant project in California, USA, in which about 10 battery shelves were melted.

For a long time, people familiar with lithium batteries can't help thinking of battery supplier LG New Energy when they see a fire in an energy storage project.

Yes, this time it also has something to do with LG new energy.

According to media reports, on the evening of February 13, 2022, an accident occurred at the Moss Landing energy storage power plant project in California, USA, in which about 10 battery shelves were melted.

This is the second accident in less than half a year after the battery overheating accident occurred in the project on September 4, 2021.

When it was built, it was the largest battery energy storage system in the world.

It is understood that the Moss Landing energy storage power station, which has had two accidents, was originally a natural gas power plant, but was later replaced by an energy storage battery power station.

The main purpose of the Moss Landing storage plant is to "trim peaks and fill valleys", that is, to help California reduce power shortages during peak hours at night, replenish the state's cheap and abundant solar photovoltaic power during the day and release it when Electroweb needs it most.

The energy storage plant began operation on December 11, 2020 and was completed as the world's largest battery energy storage system, (BESS), which contains 300MW/1200MWh lithium-ion batteries. When the energy storage power station is running at full load, it can supply power to 225000 households for 4 hours.

The battery supplier is LG New Energy.

The data show that the owner and operator of, Moss Landing energy storage power station is Vistra Energy, battery equipment provider. LG New Energy, a Korean battery giant, just listed on January 27th. Fluence is a system integrator and engineering contractor.

Reports from New Energy and Energy Storage indicate that more than 4500 battery racks have been installed in the, Moss Landing energy storage plant, based on the latest LG new energy model, TR1300.

It is reported that the TR1300 battery rack is pre-assembled in the factory before transportation, which reduces construction time and installation costs. Tests are also carried out before shipment to minimize the time required for on-site testing and commissioning.

According to the report, LG New Energy has said, "TR1300 has been tested in accordance with the UL 9540A thermal runaway fire spread standard, and the rack is designed to meet the requirements of the California building code, which believes that it is still safe to operate when the surrounding area is threatened by Earthquake activities."

Two accidents

The operator of the, Moss Landing storage plant in June 2021 said, "if market and economic conditions permit, the size and capacity of the, Moss Landing storage plant may then be expanded to accommodate up to 1500MW/6000MWh storage."

On September 4, 2021, the first phase of the, Moss Landing project caused losses of about 7% of the battery modules and other system equipment due to the start-up of the water cooling system of the battery. The accident did not cause casualties or affect the surrounding communities.

Specifically, at about 18:41 that day, the VESDA device detected smoke near containers 64, 57, 47 and 41, resulting in the release of water in pre-use area 24. When the accident occurred, a small number of joints on the hoses and pipes that were part of the battery cooling system failed, causing water to be sprayed on the battery rack. This in turn leads to short circuit and arc, which leads to battery damage and more smoke.

Now the fire broke out again at the), Moss Landing energy storage power station on February 13th. Vistra Energy subsequently issued a statement saying: "out of high caution, we have contacted the off-site emergency response department, and there were no casualties at the scene." An investigation is currently under way to determine why the security system has been activated, and we will share more information as we learn more about the situation. "

Security issues should not be underestimated

Vike Lithium noted that it was reported in October 2021 that statistics disclosed by the South Korean National Assembly showed that soft-pack batteries accounted for about 70 per cent of lithium battery fires involving electric vehicles and energy storage device (ESS) in South Korea in the past five years.

Specifically, according to the statistics provided to the Korean National Assembly by the Ministry of Industry, Trade and Resources and the Ministry of Land and Transport, among all 47 lithium battery fires in South Korea since 2017 (that is, to October 2021), 33 accidents occurred in soft package battery packs, 12 in square batteries and 2 in cylindrical batteries.

The proportion of accidents in soft-package battery packs reached 70.21%.

According to the statistics, there were 32 accidents of LG new energy products, 11 accidents of Samsung SDI products, 1 accident of SK innovation and 3 accidents of other manufacturers.

The main product of LG new energy is the soft package cell.

Summary

A gratifying change in the developing energy storage battery market is that more products with different technological routes are emerging, such as sodium ion battery, all-vanadium flow battery, iron-chromium flow battery and so on.

A common feature of these products is that they are safer.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
20 hours ago
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
20 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
20 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
20 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
20 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.
20 hours ago
Second fire! Accidents continue to occur at the largest energy storage battery power station in the world! - Shanghai Metals Market (SMM)