The word "Yan" is the first to escort the resumption of work and production of Mirador Copper Mine.

Published: Sep 10, 2020 10:02
The ball mill at the Mirado Copper Mine roared again on August 26, local time, and the mine, which had been suspended for more than five months due to the epidemic, fully resumed production. On the same day, the ore handling capacity of the concentrator reached 23891 tons. The copper concentrate produced by the Milado Copper Mine has also been transported back to Tongling Nonferrous smelter for processing. After reaching the standard, it will bring 96000 tons of copper metal to Tongling Nonferrous Metal every year.

SMM: Ecuador local time on August 26th, Mirado copper mine ball mill once again issued a roar, due to the epidemic stopped production for more than 5 months of the mine fully resumed production. On the same day, the ore handling capacity of the concentrator reached 23891 tons.

In early March, the COVID-19 epidemic raged in South America, and the Mirado copper mine in Ecuador had to press the "pause button". When the "restart" is still unknown, Tongling Nonferrous Group and China Railway Construction Copper Crown Investment Company made plans in advance, insisted on the word "strict" and introduced a series of "escort" measures to ensure the rapid restoration of production order.

After a comprehensive analysis and evaluation from the aspects of transportation of production materials and copper concentrate, organization and arrangement of personnel entry, logistics support, safety, environmental protection, occupational health work, production organization, etc., in mid-April, China Railway Construction Copper Crown Investment Co., Ltd. prepared the work Plan for the resumption of production of Merado Copper Mine; in May, the transportation of production materials was resumed to meet the needs of mineral processing production reserves; in June, the copper concentrate began to be transported inland again.

Everything revolves around the resumption of work and production. At the production site, persist in carrying out on-site hidden danger investigation, organize the backbone of party members on the spot by carrying out activities of leading party members' safety and environmental protection awareness, and carry out on-site safety inspection and on-site rectification, equipment maintenance and "three violations" investigation and handling activities. On the issue of "people", we should optimize the staffing of the post of rebirth, strictly screen the epidemic situation before personnel enter, give priority to people from areas with lower epidemic situation, and all entry personnel should be quarantined in the designated place of the company for two weeks. strengthen testing before entering and during the isolation period, and only those with negative results can enter. During the epidemic, the work rotation time was changed from one round a week to one round every eight weeks, effectively reducing personnel mobility.

Before the resumption of production, use the isolation time to conduct safety training for the employees, re-learn the job instructions, post safety risk assessment and epidemic prevention and control manual, and after the release of isolation, assess the knowledge and knowledge of the posts according to their posts. Study and summarize the work of each job post, safety prevention, epidemic prevention and control in the form of group discussion. In addition, the company leader leads the medical staff to enter the production front-line workshop for special guidance.

In more than five months of suspension of production, China Railway Construction Copper Crown Investment Company took the initiative to communicate closely with the Ecuadorian Ministry of Energy, the Ministry of the Environment and other relevant departments and local governments, and finally reached an agreement to resume production in August.

Today, China Railway Construction Copper Crown Investment Co., Ltd. focuses on production organization. On the one hand, it arranges production plans reasonably, on the other hand, through all kinds of linkage debugging, it focuses on system commissioning and water test work, and resumes work and production in a step-by-step and planned way.

The copper concentrate produced by the Milado Copper Mine has also been transported back to Tongling Nonferrous smelter for processing. After reaching the standard, it will bring 96000 tons of copper metal to Tongling Nonferrous Metal every year.

"Click to sign up: 2020 Fifth China Electrotechnical Materials supply and demand Trade Summit

Scan the code to participate in the meeting or apply to join the SMM Electrical Industry Exchange Group

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
China’s Brass Bar Imports Fell 9.94% YoY in January-February 2026
1 hour ago
China’s Brass Bar Imports Fell 9.94% YoY in January-February 2026
Read More
China’s Brass Bar Imports Fell 9.94% YoY in January-February 2026
China’s Brass Bar Imports Fell 9.94% YoY in January-February 2026
According to the latest customs data, in January 2026, China’s imports of copper-zinc alloy (brass) bars and rods were 2,050.01 mt in physical content, down 8.37% MoM and up 24.53% YoY. In February, China’s imports of copper-zinc alloy (brass) bars and rods were 1,344.87 mt in physical content, down 34.4% MoM and down 36.67% YoY, showing an overall sharp decline. Cumulative imports in January-February 2026 were 3,394.87, down 9.94% YoY cumulatively. (HS codes 74072111, 74072119, 74072190).
1 hour ago
[SMM Analysis] The Mystery Behind the Flat China Sulfuric Acid FOB Price
1 hour ago
[SMM Analysis] The Mystery Behind the Flat China Sulfuric Acid FOB Price
Read More
[SMM Analysis] The Mystery Behind the Flat China Sulfuric Acid FOB Price
[SMM Analysis] The Mystery Behind the Flat China Sulfuric Acid FOB Price
Since the beginning of 2026, the global sulfur supply has been tight, with prices continuing to rise, intensifying pressure across the industrial chain. The external environment has further exacerbated the situation: ongoing turmoil in the Middle East has disrupted shipping through the Strait of Hormuz, affecting nearly 40% of global sulfur maritime transport. Shipping costs have doubled, forcing a restructuring of trade flows.
1 hour ago
Rio Tinto Targets Mid-2030s for Arizona Copper Mine, May Export Concentrate Due to US Smelting Costs
1 hour ago
Rio Tinto Targets Mid-2030s for Arizona Copper Mine, May Export Concentrate Due to US Smelting Costs
Read More
Rio Tinto Targets Mid-2030s for Arizona Copper Mine, May Export Concentrate Due to US Smelting Costs
Rio Tinto Targets Mid-2030s for Arizona Copper Mine, May Export Concentrate Due to US Smelting Costs
Rio Tinto expects Resolution Copper mine to open by mid-2030s, may export some concentrate HOUSTON, March 24 (Reuters) – Rio Tinto aims to bring its Resolution Copper project in Arizona online by the mid-2030s, but may need to export some copper concentrate due to challenging economics for smelting in the U.S., a senior executive said on Tuesday. The mining giant recently gained control of key acreage for the project after a lengthy court battle.
1 hour ago