Home / Metal News / Jiangxi Development and Reform Commission issued a letter of opinions on the implementation Plan of electricity consumption guarantee for Renewable Energy in Jiangxi Province (trial implementation) (draft for soliciting opinions)

Jiangxi Development and Reform Commission issued a letter of opinions on the implementation Plan of electricity consumption guarantee for Renewable Energy in Jiangxi Province (trial implementation) (draft for soliciting opinions)

iconSep 7, 2020 13:17
Source:Jiangxi Development and Reform Commission
[letter issued by Jiangxi Development and Reform Commission on the implementation Plan for electricity consumption of Renewable Energy in Jiangxi Province (trial implementation) (draft for soliciting opinions) recently, the Development and Reform Commission of Jiangxi Province issued a letter on soliciting opinions on the implementation Plan for electricity consumption and Security of Renewable Energy in Jiangxi Province (trial) (draft for soliciting opinions), pointing out that all districts and cities should improve land, transportation, finance and other relevant policies. We will reduce the non-technical cost of renewable energy projects and promote the development of renewable energy projects such as wind power, photovoltaic power generation and biomass power generation in an orderly manner.

SMM: recently, the Development and Reform Commission of Jiangxi Province issued a letter on soliciting opinions on the "implementation Plan for electricity consumption and Security of Renewable Energy in Jiangxi Province (trial) (draft for soliciting opinions)", pointing out that all districts and cities should improve land, transportation, finance and other relevant policies, reduce non-technical costs of renewable energy projects, and promote the development of renewable energy projects such as wind power, photovoltaic power generation and biomass power generation in an orderly manner. The steady growth of renewable energy consumption in the province can be ensured through the orderly development of renewable energy projects in the province.

Details are as follows:

Each has district and municipal people's governments, Ganjiang New District Management Committee, Central China Energy Administration, General Institute of Hydropower and Water Conservancy Planning and Design, Jiangxi Electric Power Co., Ltd., Jiangxi Electric Power Trading Center, various market entities and relevant units:

According to the Circular of the National Development and Reform Commission and the National Energy Administration on establishing and perfecting the safeguard Mechanism for electricity consumption of Renewable Energy (NDRC Energy (2019) No. 807), and the notice of the General Office of the National Development and Reform Commission, the Comprehensive Department of the National Energy Administration, on issuing the outline of the implementation plan for the consumption and security of renewable energy at the provincial level (NDRC Energy (2020) 181, Circular of the National Development and Reform Commission and the National Energy Administration on the issuance of responsibility for Power consumption of Renewable Energy in 2020 by Provincial Administrative regions (Development and Reform Energy (2020) No. 767, In order to do a good job in the implementation of the responsibility of electricity consumption of renewable energy in Jiangxi Province, the Provincial Development and Reform Commission (Energy Bureau) organized and drafted the "implementation Plan of electricity consumption and Security of Renewable Energy of Jiangxi Province (trial) (draft for soliciting opinions)" in accordance with the requirements of the leaders of the provincial government. it is proposed to be issued by our committee after approval by the provincial government, and we are now soliciting the opinions of your unit. Please send your comments and suggestions to our committee in writing before September 10. No feedback after the expiration of the time limit is regarded as no comment.

Associate: Zhang Ziqin and Cao Hongrui

Contact: 0791-88915227 0791-88915474 (fax)

Email: jxsnyjxnyc@163.com

Attachment: implementation Plan of electricity consumption guarantee for Renewable Energy in Jiangxi Province (trial implementation) (draft for soliciting opinions)

August 28, 2020

Attachment

Implementation Plan of electricity consumption guarantee for Renewable Energy in Jiangxi Province (trial implementation) (discussion draft)

According to the Circular of the National Development and Reform Commission and the National Energy Administration on establishing and perfecting the guarantee Mechanism for electricity consumption of Renewable Energy (Development and Reform Energy (2019) No. 807), the General Office of the National Development and Reform Commission, the General Department of the National Energy Bureau issued the notice of responsibility for the consumption of renewable energy electricity in provincial administrative regions in 2020. document requirements such as notice (Development and Reform Energy (2020) No. 767), In order to do a good job in the implementation of the responsibility of electricity consumption of renewable energy in our province, the implementation plan of this consumption has been formulated according to the reality of our province.

I. guiding ideology and overall requirements

Under the guidance of Xi Jinping's thought of socialism with Chinese characteristics in the new era, we will fully implement the spirit of the 19th CPC National Congress and the second, third, and fourth Plenary sessions of the 19th CPC Central Committee, and conscientiously implement General Secretary Xi Jinping's important requirements for the work of Jiangxi. We will promote the revolution in energy production and consumption, build a clean, low-carbon, safe and efficient modern energy system, support Jiangxi Province to build a national ecological civilization demonstration zone and achieve high-quality leapfrog development. We will promote the priority consumption of renewable energy power, and establish and improve a scientific, reasonable and fair mechanism for market-oriented trading and information management of electric power, to ensure the completion of the annual minimum responsibility weight for renewable energy power consumption and the weight of non-hydropower renewable energy power consumption responsibility assigned by the state to Jiangxi Province, so as to achieve the sustained and healthy development of renewable energy.

II. Relevant subjects and division of powers and responsibilities

(1) departments in charge of energy at the provincial level

As the provincial department in charge of energy, Jiangxi Provincial Development and Reform Commission (Energy Bureau) undertakes the responsibility of allocating and implementing the responsibility of consumption responsibility in the whole province. The specific powers and responsibilities include:

(1) to be responsible for promoting the development of renewable energy in the province and promoting the production and consumption of renewable energy power in the province;

(2) to be responsible for defining the minimum responsibility weight of renewable energy power consumption (referred to as "consumption responsibility") of each market subject (hereinafter referred to as "market subject");

(3) to be responsible for supervising and urging each market subject to complete its own absorption responsibility, and to assess and publish the completion of each market subject's consumption responsibility;

(4) cooperate with the regulatory agency dispatched by the National Energy Administration and the national renewable energy information management agency to exercise their functions and powers in accordance with the rules and regulations.

(2) the municipal government of each district and the management committee of Ganjiang New District

The specific powers and responsibilities of the municipal government of each district and the management committee of Ganjiang New District include:

(1) to be responsible for promoting the development of renewable energy projects in the administrative area and promoting the production and consumption of renewable energy power in the administrative area;

(2) to be responsible for supervising and guiding the market entities in their respective administrative areas to complete their respective absorption responsibilities;

(3) to cooperate with the regulatory agencies dispatched by the National Energy Administration, the national renewable energy information management agency and the provincial energy authorities to exercise their functions and powers in accordance with the rules and regulations.

(3) Provincial power grid enterprises

State Grid Jiangxi Electric Power Co., Ltd. (hereinafter referred to as "State Grid Jiangxi Company") while fulfilling its rights and responsibilities as the main body of the market, other rights and responsibilities include:

(1) to be responsible for organizing the market entities in their respective business areas to complete their respective consumption responsibilities;

(2) to be responsible for allocating the total amount of renewable energy purchased by the power grid enterprises to the market entities in the operating area in accordance with this plan;

(3) to be responsible for taking timely measures to increase the consumption of renewable energy in the province when it is judged that the overall implementation of the consumption responsibility of the whole province can not meet the requirements of the task target issued by the state in Jiangxi Province;

(4) submit the relevant process documents, information and data of the consumer responsibility in a timely manner as required, and make a commitment to the authenticity and accuracy of the data.

(4) Provincial Power Trading Center

Jiangxi Electric Power Trading Center manages the information related to the performance of consumption responsibilities of various market entities in the province in accordance with the authorization of the provincial energy department. The specific powers and responsibilities include:

(1) to be responsible for the management of account registration and cancellation of the market subjects of the whole province;

(2) to be responsible for formulating the detailed rules for the transaction or transfer of renewable energy consumption in the province, organizing the transaction of renewable energy electricity in the province, and the over-completed transaction or transfer of renewable energy consumption (hereinafter referred to as "consumption");

(3) to be responsible for guiding the market subjects participating in the electricity transaction to give priority to completing the electric power transaction with the corresponding responsibility weight, and to remind the market subject in the links such as the examination of the medium-and long-term electric power trading contract and the publication of the electric power trading information;

(4) submit the relevant process documents, information and data of the consumer responsibility in a timely manner as required, and make a commitment to the authenticity and accuracy of the data.

(5) the main body of the market that assumes the responsibility of consumption

The market entities who bear the consumption responsibility can be divided into two categories: power sales enterprises and power users (see the third part of this plan for the specific categories and the calculation of the weight of consumption responsibility). The specific rights and responsibilities include:

(1) register the account in Jiangxi Electric Power Trading Center according to this scheme;

(2) to take the initiative to complete the weight of consumption responsibility assigned by the provincial energy department;

(3) submit the relevant process documents, information and data of the consumer responsibility in a timely manner as required, and make a commitment to the authenticity and accuracy of the data.

Third, the weight of responsibility and the mode of distribution

(1) according to the minimum consumption responsibility weight of Jiangxi Province issued by the state in 2020, the minimum total consumption responsibility weight of Jiangxi Province in 2020 is 22%, and that of non-hydropower consumption is the lowest 9%. The minimum weight of total consumption responsibility of the market entities in the province in 2020 is x%, and the lowest weight of non-hydropower consumption responsibility is x% (if the state orders Jiangxi Province to adjust the consumption responsibility, it will be adjusted accordingly). In the year after 2020, the provincial energy department will issue the annual consumption responsibility weight of Jiangxi Province according to the state, and define the annual consumption responsibility weight of each market subject every year, and distribute it according to the same weight in principle.

(2) the market subjects who bear the consumer responsibility can be divided into two categories, and the specific categories and the confirmation of the weight of the consumer responsibility are as follows:

1. The first category of market entities (electricity-selling enterprises):

(1) the State Grid Jiangxi Company shall bear the weight of consumption responsibility corresponding to its annual electricity sales (deducting the market-oriented trading electricity of market-oriented users).

(2) all kinds of enterprises that supply (sell) electricity directly to power users, independent power-selling companies and power-selling companies with the right to operate the distribution network (referred to as "distribution companies", including incremental distribution project companies), bear the weight of consumption responsibility corresponding to its annual supply (sale) electricity.

two。 The second category of market players (power users)

(3) Power users who purchase electricity directly through the electricity market (excluding those who purchase electricity through sales companies) bear the weight of consumption responsibility corresponding to their annual electricity consumption.

(4) the enterprise with its own power plant shall bear the weight of consumption responsibility corresponding to its annual electricity consumption.

(3) among the electricity sales and consumption of various market entities, agricultural electricity consumption and specially measured heating electricity shall be exempted from the assessment of consumption responsibility weight. All market entities jointly bear the consumption corresponding to the provincial network loss and plant electricity consumption.

IV. Ways of performing responsibilities and methods of calculation

(1) the main mode of implementation

Purchase or self-use renewable energy. Each market main body actually consumes the electricity of renewable energy and completes the responsibility weight of consumption.

(2) the mode of supplementary performance

1. For the purchase of excess consumption by other market entities, both parties shall independently determine the transaction or transfer price, and the funds shall be raised by the purchaser.

two。 If you buy a green certificate, the amount of electricity of renewable energy corresponding to the green certificate shall be recorded as consumption.

3. In the case that the annual consumption responsibility of the province cannot be fulfilled, the transaction or transfer of renewable energy electricity, consumption and green card across provincial administrative regions shall be carried out.

(3) calculation of consumption

1. Renewable energy purchased through the market

(1) the renewable energy purchased by Jiangxi Company of the State Grid is first used to complete the responsibility weight of residents in the operating area, important public utilities and public welfare services, and non-market-oriented electricity consumption. If there is any surplus, the State Grid Jiangxi Company shall, in accordance with the proportion of total electricity consumption of renewable energy and the proportion of electricity consumption of non-water renewable energy in the operating area, be included in the consumption of various market entities in equal proportion, and will be distributed according to the principle of free compensation at the initial stage, and will be adjusted in due course according to the progress of power market reform.

(2) the amount of renewable energy in the market-oriented transaction of electricity in the province shall be included in the consumption of the main body of the electricity purchase market according to the settlement of the transaction. The proportion of renewable energy in the amount of electricity traded across provincial administrative regions shall be confirmed in accordance with the relevant power purchase agreement.

two。 Electricity of renewable energy for self-use

According to the electricity consumption of renewable energy for spontaneous self-use measured by the State Grid Jiangxi Company, all the electricity consumption of renewable energy is included in the main body of the spontaneous self-use market. In the case that the main body of the spontaneous self-use market overfulfills the consumption amount, the over-completion part can be used for transaction or transfer.

3. Completion of consumption by supplementary (alternative) mode

The consumption amount purchased from other market entities who have overfulfilled the responsibility weight or the consumption amount converted from the purchase of green cards (for the State Grid Jiangxi Company, including the relevant consumption amount through inter-provincial power transactions) shall be included in the consumption amount of the buyer. The amount of consumption sold or transferred by the main body of the market, as well as the corresponding amount of consumption corresponding to the sale of green certificates, will no longer be included in their own consumption. In accordance with the principle of equality of rights and responsibilities, the corresponding consumption of agricultural electricity or specially measured heating electricity exempted from the assessment of the weight of consumption responsibility can not be used or transferred in transactions.

Process management and information submission

(I) process management documents

(1) the list of market entities responsible for consumption: it shall be organized and compiled by Jiangxi Electric Power Trading Center and submitted to the provincial energy department before the end of February each year, which shall be announced by the provincial energy department to the whole society in the first quarter of each year.

(2) the list of the responsibility weight of each market subject: the provincial energy department shall make a comprehensive demonstration according to the task index issued by the state in Jiangxi Province and the actual situation of the province, and confirm and publish it on an annual basis.

(3) organizational rules for the implementation of the responsibility weight of renewable energy power consumption: it shall be prepared by the State Grid Jiangxi Company in accordance with this plan and submitted to the provincial energy department for approval before implementation.

(4) the detailed rules for the transaction (transfer) of electricity consumption of renewable energy in the province: it shall be formulated by Jiangxi Electric Power Trading Center in accordance with the requirements of relevant national documents and combined with the actual situation of the province, and shall be submitted to the competent energy department at the provincial level for approval before implementation.

(5) Renewable energy power consumption plan: the market entities shall formulate according to the current year's consumption responsibility weight list, put forward the requirements and preliminary arrangements for the completion of the consumption task, and submit it to the districts and cities where they are located, the national network Jiangxi Company and Jiangxi Electric Power Trading Center. Enterprises with self-owned power plants that are not connected to the public power grid shall formulate annual renewable energy power consumption plans, which shall be summarized and submitted to the provincial energy authorities and Jiangxi Electric Power Trading Center through their respective districts and cities.

(6) the commitment to fulfill the responsibility of consumption: it shall be issued by all market entities and submitted to Jiangxi Electric Power Trading Center together with the renewable energy power consumption plan, promising to complete the responsibility weight of renewable energy power consumption assigned by the provincial energy department, report the completion and relevant data as required, and be responsible for the authenticity and accuracy of the data.

(2) requirements for information submission

(1) the monthly report on the completion of the responsibility weight of the market subject: it shall be compiled by each market subject and submit the completion of the responsibility weight of the unit last month to the district, city and Jiangxi Electric Power Trading Center within the first 3 working days of each month.

(2) the analysis and evaluation report on the completion of the consumption responsibility weight of the whole province: compiled by Jiangxi Electric Power Trading Center and regularly submitted to the regulatory agency dispatched by the State Energy Administration, the national renewable energy information management agency and the provincial energy department. Among them, the quarterly report should be submitted within 10 working days before the next quarter, and the annual report should be submitted in January of the following year.

(3) Annual report on the completion of the organization of consumer responsibility weight: compiled by Jiangxi National Network, in January each year, the State Energy Administration dispatched regulatory agencies, the national renewable energy information management agency and the provincial energy department in charge of energy to report the completion of the work of the responsibility weight organization in the previous year in the business area.

(4) Renewable energy electricity-related trading process: submitted by Jiangxi Electric Power Trading Center in accordance with the requirements of the regulatory agency dispatched by the State Energy Administration, the national renewable energy information management agency and the provincial energy department.

(5) data related to the consumption of market entities: provided by various market entities in accordance with the requirements of the regulatory agencies dispatched by the State Energy Administration, the national renewable energy information management agencies and the provincial energy authorities, it is collected and submitted through the districts and cities where the market subjects are located.

VI. Job requirements and safeguard measures

(1) to raise awareness and promote the orderly development of renewable energy projects. All localities and units should firmly establish the concept of high-quality development, from the height of implementing the "six stability and six guarantees" and promoting the revolution in energy production and consumption, regard the orderly development of renewable energy projects as an important measure to achieve the security of energy supply in the province and promote the transformation of energy structure. All districts and cities should improve relevant policies on land, transportation and finance, reduce the non-technical cost of building renewable energy projects, and promote the development of renewable energy projects such as wind power, photovoltaic power generation and biomass power generation in an orderly manner. The steady growth of renewable energy consumption in the province can be ensured through the orderly development of renewable energy projects in the province.

(2) to optimize the environment and ensure the consumption of renewable energy power network. Power grid enterprises at all levels should strengthen the connection and consumption services of renewable energy projects to ensure the dispatching and safe operation of renewable energy projects in the province according to the base load. It is necessary to do a good job in measuring the new consumption capacity of renewable energy power generation and provide early warning information in a timely manner. It is necessary to speed up the construction of supporting power grid projects for renewable energy projects in the province, optimize the grid structure, and create conditions for renewable energy projects to be connected to the power grid. Jiangxi Electric Power Trading Center should provide service guarantee for renewable energy power trading, and if it is necessary to carry out inter-provincial administrative regional power transactions, it should give priority to the purchase of renewable energy electricity.

(3) strengthen monitoring and strengthen the management of renewable energy consumption process. Departments in charge of energy at all levels should attach great importance to the process management of the achievement of the annual target of responsibility for renewable energy consumption, and do a good job in process monitoring in conjunction with relevant departments and units. It is necessary to make full use of modern information management means to strengthen the monitoring and application of renewable energy data so as to provide technical support for the management of renewable energy consumption process. It is necessary to regularly organize and carry out analysis and evaluation of renewable energy consumption in various localities and various market entities, and study and formulate safeguard measures when there is a deviation in the achievement of annual targets, so as to make up for the shortcomings in consumption in a timely manner.

(4) compaction responsibility and improve the guarantee mechanism for the consumption of renewable energy. Provincial energy departments should strengthen research in the light of reality, constantly improve the relevant mechanisms such as the distribution of responsibility for renewable energy consumption and supervision and assessment, and formulate other safeguard measures in due course. Urge all localities and market entities to implement the security requirements for the consumption of renewable energy power. Each market entity shall consciously fulfill the responsibility of renewable energy consumption according to the annual responsibility weight, and complete the account registration or withdrawal in Jiangxi Electric Power Trading Center within 10 working days after the issuance of this plan. Qualified market entities are encouraged to voluntarily complete the minimum consumption responsibility weight higher than the assigned minimum consumption responsibility weight, and the energy consumption that exceeds the minimum consumption responsibility weight shall not be included in the energy consumption assessment. Market entities that have unfulfilled weight targets, refuse to fulfill their consumption obligations or provide fraudulent consumption data shall be dealt with by the regulatory agencies dispatched by the State Energy Administration and provincial energy authorities in accordance with the rules and regulations.

VII. Supplementary provisions

(1) this plan shall be implemented as of the date when it is issued by the people's Government of Jiangxi Province.

(2) the Jiangxi Provincial Development and Reform Commission (Energy Bureau) is responsible for explaining this plan.

(3) if the relevant contents of this programme are no longer applicable as a result of the adjustment of the national policy, it shall be implemented in accordance with the new national policy.

 

"Click to sign up: 2020 Tin Industry chain Trading Summit

Scan the code to participate in the meeting or apply to join the SMM tin industry exchange group

Photovoltaic
policy
power grid
production capacity