[SMM News] European Manganese Industry: the Chvaletice Manganese Project will provide high purity manganese products for large-scale lithium battery manufacturing

Publicado: Jun 5, 2019 14:33
Fuente: SMM

SMM6, May 5-(Euro Manganese) of the European manganese industry provides an update on the operation of Chvaletice's manganese project, which is located in the Czech Republic and is wholly owned by the European manganese industry. The agreement includes the signing of strategic agreements with consumers of battery raw materials, feasibility studies and updates on demonstration plants. This includes the issuance of two major contracts related to the launch of the project feasibility study and its licensing and environmental impact assessment procedures, as well as some positive developments in the local communities adjacent to the project.

Mr. Marco Romero, President and Chief Executive Officer of the European Manganese Industry, commented, "We are pleased to report on the company's first important potential cooperative customer, the appointment of two main contractors, and we have decided to move the project to the feasibility study stage. We demonstrate the continued progress in the proposed development of the plant and the further development of a valuable relationship with the local community. "

 

Sign the first strategic agreement

In early May 2019, the company signed a strategic agreement with potential customers on high-purity manganese products to provide a strategic and technical cooperation framework for large-scale lithium-ion battery manufacturing, including production. High-performance lithium-ion batteries in multiple market segments, including electric vehicles. Under the strategic agreement, the two sides intend to cooperate in order for the company to propose the design and construction of the Chvaletice manganese project plant to meet the environmental quality and long-term supply requirements of high-purity manganese products from counterparties and their customers.

Under the terms of the agreement, the company plans to deliver a specified amount of high-purity manganese sulfate monohydrate ("HPMSM") ("model material") to counterparty plants in early 2020. Demonstration materials will be provided in batches and tons of finished product samples for customer testing and evaluation at the company's demonstration plant. Upon completion of the testing and identification of the model materials, the parties intend to negotiate with a view to reaching the terms and provisions of an off-take agreement on the supply and purchase of high-purity manganese products produced by the project.

The company will continue to engage in active discussions with several consumers of high-purity manganese products in Europe, Asia and North America, with the goal of entering into similar strategic, commercial, technical and framework agreements with these companies for testing and certification. The high-purity manganese products of the project are designed to enable the parties to enter into binding off-take agreements and long-term commercial or strategic relationships.

 

Feasibility study, main contractor and demonstration plant

Following the completion of the preliminary economic assessment ("PEA") earlier this year, the company plans to advance the project to the feasibility phase. Proposals in the list of engineering companies are being evaluated and it is expected that the relevant contracts for the feasibility study will be awarded to two or more parties during the second quarter of 2019.

The company has appointed Tetra Tech Canada Inc. ("Tetra Tech") as the owner's engineering representative to supervise other consultants and service providers related to the feasibility study and to prepare a study report on the feasibility of the National Instrument 43 / JORC project. In addition, a department of Bilfinger Tebodin (Bilfinger SE, Czech Republic) has been appointed to prepare the description and notification of the project for submission to the Czech Ministry of the Environment to advance the licensing and environmental assessment procedures for the project.

Tetra Tech carried out some early feasibility studies during the quarter ended 31 March 2019. Therefore, subject to the acquisition of the remaining feasibility study contract, EMN expects the feasibility study to be completed by early 2020. As the feasibility phase progresses, the company hopes to continue to assess potential value-added opportunities for the project. These include the potential to optimize building size and layout, equipment selection, solid-liquid separation methods, alternative solution purification methods, manganese sulfate crystallization techniques, leaching methods, waste generation and recovery, and minimizing energy and water consumption. In cooperation with one or more potential consumers of high-purity manganese products, the company also intends to assess the feasibility of building one or more satellite manganese metal dissolution plants at the customer's NMC precursor plant. This will enable the company to sell manganese sulfate solutions instead of granular manganese sulfate monohydrate, thus eliminating the crystallization steps at these locations. The company also plans to assess the possibility of selling magnesium sulfate, a by-product, for agricultural purposes. These and other opportunities will be assessed within the scope of the design study of the feasibility study.

The establishment and commissioning of a demonstration plant in the Czech Republic will also be planned and prepared, which will provide large quantities of multi-tonne finished product samples for customer evaluation and identification. The plant aims to replicate the entire process flow chart proposed in PEA and to produce the equivalent of 100kg of HPMSM per day. Some potential customers have expressed interest in testing and identifying these products for the production of lithium-ion batteries and cathode precursor materials, combined with existing nickel, cobalt and lithium products. The demonstration plant will also achieve process optimization and testing of the final product and serve as a testing and training facility for future operators. Design work has been initiated and the company is currently evaluating turnkey plant supply proposals for completion and performance assurance support, with the goal of signing contracts during the second quarter of 2019. The company expects the plant to be completed by the end of 2019 and to provide the first batch of finished product samples to potential customers in early 2020.

 

Rezoning of land for projects and land purchases

The adjacent towns of Chvaletice and Trnavka, where the tailings of the company project are located in the west and east of the project, respectively, voted unanimously to initiate the rezoning process. According to the municipal land use plan, the base land for the tailings of the project.

In mid-May 2019, the Company entered into a conditional sale and purchase agreement with the city of Trnavka for the purchase of a narrow 2.96 hectares of land near the Chvaletice tailings. The land is mainly used for the infrastructure of the project and the establishment of a visual and acoustic buffer zone between the project and the village of Trnavka. The payment period is several years and is linked to specific licensing milestones.

Mr. Marco Romero, President and Chief Executive Officer of Manganese Europe, said, "We are pleased that our relations with the adjacent communities of Chvaletice and Trnavka continue to develop. Our team is working to ensure that local communities are informed and create meaningful opportunities for them to participate in the evaluation and planning of the Chvaletice manganese project, and their input is integrated into their development plans. It also aims to bring them overwhelming positive benefits, including the restoration of brown areas affected by the environment. Our goal remains to build long-term, respectful and collaborative relationships with these communities, while ensuring that projects are seamlessly integrated into the environmental, social and economic structures of the region. "

"[investment must see] Trade friction news flying all over the metal how to win in chaos?

"Click to enter the registration page

Scan QR code and apply to join SMM metal exchange group, please indicate company + name + main business

 

Declaración de Fuente de Datos: Excepto la información disponible públicamente, todos los demás datos son procesados por SMM basándose en información pública, comunicación de mercado y confiando en el modelo de base de datos interna de SMM. Son solo para referencia y no constituyen recomendaciones para la toma de decisiones.

Para cualquier consulta o para obtener más información, por favor contacte: lemonzhao@smm.cn
Para más información sobre cómo acceder a nuestros informes de investigación, contacte con:service.en@smm.cn
Noticias relacionadas
[SMM News] La reactivación de Finniss de Core Lithium alcanza un hito clave
hace 51 minutos
[SMM News] La reactivación de Finniss de Core Lithium alcanza un hito clave
Leer más
[SMM News] La reactivación de Finniss de Core Lithium alcanza un hito clave
[SMM News] La reactivación de Finniss de Core Lithium alcanza un hito clave
El 8 de septiembre, Core Lithium anunció que su proyecto de litio Finniss, en el Territorio del Norte de Australia, había producido su primer concentrado de espodumeno en la planta de procesamiento reacondicionada. El hito se alcanzó unos seis meses después de que la empresa tomara la decisión final de inversión para reiniciar Finniss en marzo de 2026, en línea con su objetivo para el trimestre de septiembre. La minería en la mina a cielo abierto Grants se reanudó en mayo, seguida del reinicio de las operaciones de trituración en agosto, mientras que la planta de procesamiento se encuentra actualmente en fase de puesta en marcha y optimización. Según Core Lithium, se espera que las mejoras en la planta de procesamiento aumenten la liberación del mineral y las tasas de recuperación, a la vez que incrementen la capacidad de procesamiento en aproximadamente un 20 %, hasta 1,2 millones de toneladas anuales. La empresa mantiene el objetivo de realizar el primer envío de concentrado de espodumeno recién producido en el cuarto trimestre de 2026, mientras avanza también el desarrollo de la mina subterránea BP33.
hace 51 minutos
[Batería de litio: CALB firma acuerdo para instituto de investigación en Hefei y contratará a más de 2.000 empleados de I+D]
hace 1 hora
[Batería de litio: CALB firma acuerdo para instituto de investigación en Hefei y contratará a más de 2.000 empleados de I+D]
Leer más
[Batería de litio: CALB firma acuerdo para instituto de investigación en Hefei y contratará a más de 2.000 empleados de I+D]
[Batería de litio: CALB firma acuerdo para instituto de investigación en Hefei y contratará a más de 2.000 empleados de I+D]
CALB firmó un acuerdo de cooperación con el gobierno del condado de Changfeng el 8 de septiembre, estableciendo oficialmente su instituto de investigación en Hefei. El proyecto incluye líneas piloto, laboratorios de I+D y centros de pruebas para baterías de litio y productos relacionados. La presidenta de CALB, Liu Jingyu, afirmó que el instituto construirá un ciclo de innovación de cadena completa desde la I+D hasta la verificación piloto y las pruebas de productos, con la contratación de más de 2.000 empleados de I+D. Las fases I y II de la base de CALB en Hefei están en producción, la fase III está a punto de comenzar y la fase IV está en construcción; a plena capacidad se convertirá en la mayor base de producción de CALB en China.
hace 1 hora
Reseña diaria de SMM: Los precios del carbonato de litio al contado bajaron ligeramente el 9 de septiembre
hace 1 hora
Reseña diaria de SMM: Los precios del carbonato de litio al contado bajaron ligeramente el 9 de septiembre
Leer más
Reseña diaria de SMM: Los precios del carbonato de litio al contado bajaron ligeramente el 9 de septiembre
Reseña diaria de SMM: Los precios del carbonato de litio al contado bajaron ligeramente el 9 de septiembre
Hoy, los precios spot de carbonato de litio de grado batería de SMM bajaron ligeramente en comparación con la jornada anterior. El contrato de carbonato de litio 2701 abrió hoy a la baja en 142.900 yuanes/t, luego cayó rápidamente tras la apertura, alcanzando un mínimo cerca de 140.600 yuanes/t, antes de consolidarse y rebotar. En las primeras operaciones, los alcistas ganaron impulso y los precios se dispararon hasta un máximo intradía de 144.400 yuanes/t, antes de encontrar presión vendedora de los bajistas y retroceder por debajo de la línea de precio medio. Hacia el mediodía, alcistas y bajistas forcejearon repetidamente en el rango de 140.000-142.000 yuanes, con los precios moviéndose lateralmente en torno a la línea de precio medio. Por la tarde, el mercado se mantuvo en un punto muerto entre alcistas y bajistas, y los precios fluctuaron ligeramente al final de la sesión, cerrando cerca de 142.000 yuanes/t. El contrato finalmente se liquidó con una caída del 0,69% en 142.000 yuanes/t, con un aumento del interés abierto de 6.860 lotes. En el mercado spot, los compradores intermedios mantuvieron un ritmo de compra en las caídas, pero algunas plantas de materiales fueron más cautelosas, presionando sus precios de compra aceptables por debajo de 140.000 yuanes/t. Las plantas químicas de litio aguas arriba continuaron absteniéndose de vender pedidos spot y mantuvieron los precios firmes, con una liberación limitada de cargamentos a bajo precio. Las discrepancias de precios entre vendedores y compradores persistieron, mientras que las consultas del mercado fueron relativamente activas y las transacciones reales estuvieron impulsadas principalmente por la demanda rígida.
hace 1 hora
[SMM News] European Manganese Industry: the Chvaletice Manganese Project will provide high purity manganese products for large-scale lithium battery manufacturing - Shanghai Metals Market (SMM)