Recently, Tangshan production restriction policy has emerged frequently, which seems to have a tendency to be strict. Boosted by the news, early trading continued to rise in the evening, black system strong operation, thread 1905 rose 1.06 per cent, hot volume rose 1.62 per cent, iron ore rose 0.64 per cent. However, from the SMM survey data, the thread supply in December is still incremental, the main steel thread production ring ratio increased by 5%, as the demand continues to shrink, the thread downward space will still be larger than the upward space, and the trend of short and long space will remain unchanged. In terms of varieties, the fundamentals of iron ore are still stronger than those of finished materials. According to SMM steel survey data, the current port inventory is still low, down 4.73 million tons from the same period last year, steel plant inventory compared with the same period last year also decreased by 5 to 6 days.

Recently, the relevant departments in Tangshan City reported on the progress of the autumn and winter off-peak production in the iron and steel industry from 2018 to 2019. The relevant contents are as follows:

1. The arrangement of off-peak production in autumn and winter in iron and steel industry determines that the implementation period of off-peak production in autumn and winter is from October 1, 2018 to March 31, 2019 (a total of 182 days). The off-peak production performance of iron and steel enterprises in the whole city is classified. Considering the actual situation, the production capacity of blast furnace in autumn and winter is 18.5922 million tons. The actual output of the blast furnace exceeded the peak limit of 2.71 million tons in the heating season last year, and the proportion of production limit was adjusted and controlled by 31.55 per cent.

Second, supervision and inspection of the implementation of the wrong peak production plan in view of the iron and steel enterprises on the autumn and winter wrong peak production limit task is not in place. The clear rectification and reform requirements are put forward: first, the strict governor should not replace the wrong peak production limit by means of blast furnace air control and oxygen reduction, short-term furnace shutdown maintenance, etc., and the reduction of output can not be accepted as the output limit of the wrong peak. The second is to check the minimum production load of guaranteed heating. It is preliminarily determined that, with the exception of five iron and steel enterprises, which can appropriately extend the time limit for staggered peak production, other enterprises are carried out according to the existing production plan for reaching the wrong peak in the city, and the production time of the wrong peak shall not be extended at will. It is necessary to limit the production of Xiancheng in autumn and winter before March 31, 2019.

Third, the actual implementation of the off-peak production in Tangshan iron and steel enterprises can be divided into two categories. First, according to the city to reach the wrong peak production plan requirements in place, including 9 counties (cities) 24 iron and steel enterprises. Second, according to the city to reach the wrong peak production plan requirements have not been implemented in place, including 6 counties (cities) 11 iron and steel enterprises. At present, it is actively coordinating and supervising counties (cities) and enterprises to adjust and implement the wrong peak production plan according to the requirements, and report it to the relevant departments for the record.

IV. The next step is to earnestly implement the main responsibility, and the local steel enterprises should strictly implement the main responsibility of the wrong peak production, and the wrong peak production tasks should be implemented in the specific equipment, working procedures, and specific time periods. Ensure that all production restrictions are fully implemented as required. The second is to strengthen regular supervision and inspection. Third, we should closely combine the early warning response of heavily polluted weather with the off-peak production, supervise iron and steel enterprises to adjust the "one plant, one policy" plan in time, increase the stopping and limiting production of blast furnace, and increase the proportion of stopping and limiting production during the period of heavily polluted weather. To ensure the successful completion of the off-peak production task in the iron and steel industry in autumn and winter.

Tangshan
production limit news
black rebound
short sky

For queries, please contact Michael Jiang at michaeljiang@smm.cn

For more information on how to access our research reports, please email service.en@smm.cn

Related news

SMM Events & Webinars

All