Home / Metal News / SMM Update of Chinese NPI Projects in Indonesia in August

SMM Update of Chinese NPI Projects in Indonesia in August

iconAug 17, 2015 16:23
Source:SMM
How Chinese NPI projects in Indonesia progress? Shanghai Metals Market gives you the latest update of major projects as of early August.

SHANGHAI, Aug. 17 (SMM) – How Chinese NPI projects in Indonesia progress? Shanghai Metals Market gives you the latest update of major projects as of early August.

Ifishdeco is also expected to postpone the commissioning of its NPI project in December 2015, with equipment being installed. Ningbo Brillimetal Company is expected to put off commissioning of its NPI project in Indonesia to December 2015 against the sluggish market. Jiangpu Stainless Steel started both of its two 30 m³ blast furnaces in early August, with monthly NPI output of 1,000 tonnes. 

Huadi Steel Group is erecting its plants, and will put online the project during March-April 2016 at the earliest. 

Beijing Shenwu Environment & Energy Technology Corp.-Titan will unlikely put online its Indonesian project in 2015 due to technical factor. 

For news cooperation, please contact us by email: sallyzhang@smm.cn or service.en@smm.cn.

npi
china npi output
Indonesia export ban

For queries, please contact William Gu at williamgu@smm.cn

For more information on how to access our research reports, please email service.en@smm.cn

Related news

SMM Events & Webinars

All