Minmetals 23rd Construction Co., Ltd. successfully produced ferronickel in its first project in Indonesia

게시됨: May 12, 2025 14:07

On April 27, the first phase of the CNI nickel-iron RKEF project in Indonesia, undertaken by the International Business Department of Minmetals Twenty-Three Metallurgical Construction, successfully produced nickel-iron, marking the official entry of the project into the trial production phase. Behind this significant milestone was the unwavering perseverance and dedication of the project team, who overcame the "three major challenges" of rotary kiln hoisting, electric furnace construction, and timely iron production over more than 700 days and nights, setting multiple new records for the company in the field of overseas metallurgical construction.

Meticulous

Successful Completion of Rotary Kiln Hoisting

The rotary kiln for the first phase of the CNI nickel-iron RKEF installation project in Indonesia, with a diameter of 5.8 meters and a length of 130 meters, is the core equipment of the RKEF nickel-iron smelting process. Its installation quality directly affects the normal operation of the entire production line. The team innovatively adopted the "segmented pre-assembly + laser positioning" method, controlling the installation accuracy to the millimeter level.

The project department organized multiple discussions, refinements, and revisions of the hoisting plan, developing a safe, economical, and efficient hoisting scheme. At the same time, they fully coordinated with the supervision and construction parties, carefully reviewing each construction phase. Before hoisting, comprehensive inspections were conducted on the crane, ground, slings, and equipment body, and all workers were briefed on safety techniques.

The project began on-site bearing seat grinding in November 2023; in December 2023, the base and support rollers were hoisted, and the cylinder was assembled on the ground; in January 2024, the first section of the cylinder was officially hoisted, and over 1,000 mt of the kiln body was hoisted within one month, completing the aerial welding of the cylinder in just 10 days, setting a new industry record for efficient construction.

Chasing the Wind and the Moon

Ensuring Smooth Progress of Electric Furnace Construction

The rectangular electric furnace involved in the first phase of the CNI nickel-iron RKEF installation project in Indonesia had only been constructed by China Fifteenth Metallurgical Construction domestically, and the furnace for this project was larger in scale and more complex in process. As a key piece of equipment, the construction of the electric furnace required immense effort from the project team. Due to the remote location of the project, material procurement faced numerous constraints. To address urgent material shortages, the project department implemented a multi-point layout strategy, stationing procurement personnel domestically and in Jakarta and Kendari to ensure timely material supply.

During the Chinese New Year, the project team remained on duty, implementing precise strategies and completing the installation of the electric furnace and rotary kiln with high quality. Particularly in key processes such as the refractory brick laying of the electric furnace and the refractory material pouring of the rotary kiln, the work was completed 10 days ahead of schedule, with quality indicators exceeding national standards, laying a solid foundation for the successful start of production of the electric furnace and also filling the company's gap in the field of rectangular electric furnace construction.

On March 7, the 72MVA rectangular electric furnace was successfully started. ENFI, the general contractor of the project, sent a letter of commendation to the project team, praising the project management team for its outstanding professional capabilities and the spirit of overcoming difficulties during the project construction. The letter stated that the team "ensured efficient contract performance through scientific management" and "strictly controlled quality throughout the entire process," and specifically mentioned that "despite the compressed project duration, the construction tasks were completed ahead of schedule, fully demonstrating your company's strength in the field of metallurgical construction."

Pursuing Excellence

Striving to Achieve the Tapping Target

The "April 30 tapping" period target set by the owner was unanimously regarded as "nearly impossible to achieve" by the supervisor and the general contractor. The project department implemented a "two-shift" operation mode and established an "hourly" progress control system. All members worked day and night in a fierce race against time.

Focusing on the goal of tapping on schedule, the project department collaborated with the general contractor, supervisor, and other relevant units to work backwards from the project deadline, subdivide the construction characteristics of each subproject, and communicate and coordinate in advance the supply of personnel, machinery, and material spare parts. From the successful power transmission to the electric furnace on April 6, to the successful slag tapping on April 18, and then to the successful production of ferronickel on April 27, the project team set a record for the company's large-scale rectangular ferronickel electric furnace, taking only 21 days from the start of power transmission to the production of ferronickel. The tapping period was achieved 3 days ahead of the original plan.

Like a boat navigating the vast sea or a horse standing atop Kunlun Mountain, the International Business Department of Minmetals 23rd Construction Group Co., Ltd. will stride forward with the tide of the times, seizing the opportunity to accelerate the construction of a new highland for metallurgical construction under the "Belt and Road" Initiative. Adhering to the development philosophy of cooperation, mutual benefit, and win-win results, the department will introduce more Chinese solutions, technologies, and construction practices to the participating countries.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
관련 뉴스
【SMM 니켈 플래시】엘니뇨 날씨로 IMIP 생산 리스크 증가
14시간 전
【SMM 니켈 플래시】엘니뇨 날씨로 IMIP 생산 리스크 증가
더 보기
【SMM 니켈 플래시】엘니뇨 날씨로 IMIP 생산 리스크 증가
【SMM 니켈 플래시】엘니뇨 날씨로 IMIP 생산 리스크 증가
2026년 엘니뇨 현상이 계속 강화되고 있으며, 국제 기후 모니터링에 따르면 이번 엘니뇨는 기록상 가장 강력한 엘니뇨 중 하나가 될 수 있다고 합니다. 인도네시아는 이미 상당한 폭염과 건조 상태를 겪고 있으며, 엘니뇨는 9월에 정점에 이를 것으로 예상됩니다. SMM에 따르면 현재 IMIP의 물 부족은 주로 탄소강 생산에 영향을 미치고 있으며, 니켈 생산에는 아직 영향이 없습니다. 그러나 건조한 날씨와 물 부족이 지속될 경우 산업용수 공급에 대한 추가 압박으로 니켈 생산 감축 위험이 커질 수 있습니다.
14시간 전
데이터: 상하이선물거래소(SHFE), 다롄상품거래소(DCE) 시장 동향 (9월 2일)
15시간 전
데이터: 상하이선물거래소(SHFE), 다롄상품거래소(DCE) 시장 동향 (9월 2일)
더 보기
데이터: 상하이선물거래소(SHFE), 다롄상품거래소(DCE) 시장 동향 (9월 2일)
데이터: 상하이선물거래소(SHFE), 다롄상품거래소(DCE) 시장 동향 (9월 2일)
다음 표는 2026년 9월 2일 상하이선물거래소(SHFE)와 다롄상품거래소(DCE)의 철금속 및 비철금속 거래 동향을 보여줍니다.
15시간 전
[SMM 니켈 플래시 뉴스] 일일 업데이트 — 2026년 9월 2일
16시간 전
[SMM 니켈 플래시 뉴스] 일일 업데이트 — 2026년 9월 2일
더 보기
[SMM 니켈 플래시 뉴스] 일일 업데이트 — 2026년 9월 2일
[SMM 니켈 플래시 뉴스] 일일 업데이트 — 2026년 9월 2일
가격 측면에서 이번 주는 9월 상반월 HMA 가격 주기의 첫 주에 해당하며, HMA는 톤당 16,733.33달러를 기록했다. 인도네시아 니켈 광석 CIF 평균 가격은 세 등급 모두 조정되었다. • Ni 1.3%: CIF 평균 가격 $30/wmt • Ni 1.4%: CIF 평균 가격 $52.8/wmt • Ni 1.5%: CIF 평균 가격 $59.2/wmt ________________________________________ 인도네시아 정책 및 DSI ICOMEX 업데이트 — 2026년 9월 2일 인도네시아 니켈 광석 시장은 여전히 관망세를 유지하고 있으며, 시장은 추가적인 RKAB 승인과 잠재적인 쿼터 조정을 면밀히 주시하고 있다. 한편, DSI는 광물 및 전략 원자재 수출을 모니터링하고 규제하기 위한 디지털 플랫폼인 ICOMEX 개발을 추진하고 있다. 이 플랫폼은 계약, 가격, 광석 등급, HS 코드, 선박, 목적지 및 결제 정보를 포함한 주요 수출 관련 데이터를 단계적으로 통합할 것으로 예상된다. ICOMEX의 개발은 수출 데이터 투명성, 규제 감독 및 가격 모니터링을 개선하는 동시에 정부에 광물 수출 흐름에 대한 보다 포괄적인 시각을 제공할 것으로 기대된다. 주요 니켈 생산 지역의 기상 조건은 전반적으로 관리 가능한 수준을 유지하고 있으나, 국지적인 폭우로 인해 채굴 및 물류에 일시적인 차질이 발생할 가능성은 여전히 존재한다. 시장은 또한 리모나이트 광석에 대한 HPM 공식의 잠재적 개정을 기다리고 있다. 가격 결정 메커니즘의 변경, 특히 수반 금속 처리 및 보정 계수와 관련된 변경은 리모나이트 가격과 HPAL 원료 경제성에 영향을 미칠 수 있다. 전반적으로 시장은 신중한 태도를 유지하고 있으며, RKAB 승인, ICOMEX 개발, 기상 조건 및 잠재적인 리모나이트 HPM 개정이 단기적으로 주목해야 할 핵심 요인이다.
16시간 전
Minmetals 23rd Construction Co., Ltd. successfully produced ferronickel in its first project in Indonesia - Shanghai Metals Market (SMM)