Green Hydrogen Project Tracking - Southwest Research & Design Institute of Chemical Industry, SINOCHEM Wins Bid for Goldwind Water Electrolysis Hydrogen Production Plant T+EPC

게시됨: May 7, 2025 10:02

Recently, the announcement of the successful bidder for the T+EPC Engineering, Procurement, and Construction (EPC) contract for the Phase I project of the 2 million kW wind power-to-green hydrogen and 500,000 mt green methanol demonstration project's electrolytic water hydrogen production plant was released.

According to the announcement, the bid winner is Southwest Research & Design Institute of Chemical Industry Co., Ltd.

According to the tender notice, the T+EPC EPC contract for the Phase I project of the 2 million kW wind power-to-green hydrogen and 500,000 mt green methanol demonstration project's electrolytic water hydrogen production plant, operated by Goldwind Green Energy Chemical (Xing'an League) Co., Ltd., is located in the Economic and Technological Development Zone of Xing'an League, Inner Mongolia Autonomous Region.

Procurement scope: Starting from the battery limit of the hydrogen production unit, it includes units such as hydrogen storage, hydrogen compression, electrolyte preparation and circulation, waste electrolyte storage and export, nitrogen generation system and storage, closed-loop circulating water system (used only for electrolyte cooling), instrument and cabinet room, power transformation and distribution station, circulating water station, desalted water station, heating water station, initial rainwater and emergency water pool, up to the system where hydrogen and oxygen are sent out through pipelines. The contractor is required to design the overall production mode and propose public auxiliary facilities, while the supplier needs to make reasonable designs based on the fluctuating conditions of green electricity and comprehensively consider the layout of the hydrogen production workshop, among other factors.

Planned construction period: The supplier shall arrange the construction period reasonably, with the mid-term handover scheduled for November 30, 2025.

This project does not accept consortium participation in negotiations.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn