1.199 yuan/Wh! Tender for 246 MW/492 MWh Distributed ESS Power Station in Jiangsu

게시됨: Apr 29, 2025 10:04

Polaris Energy Storage Network News: On April 27, a tender announcement for the 246MW/492MWh distributed energy storage power station project in Jiangdu Economic Development Zone, Yangzhou, Jiangsu Province, was released. The documents indicate that the total investment for the project is approximately 590 million yuan, equivalent to a unit price of 1.199 yuan/Wh. The planned construction period is 365 calendar days, and joint bidding is not accepted.

Below is the original tender announcement:

Tender Announcement for the 246MW/492MWh Distributed Energy Storage Power Station Project in Jiangdu Economic Development Zone

I. Tender Conditions

This tender project, the "246MW/492MWh Distributed Energy Storage Power Station Project in Jiangdu Economic Development Zone," has been approved for construction. The bid inviter is "Yangzhou Jiangdu Jiangzhou Industrial Development Co., Ltd." The funding for the tender project is self-raised (source of funds), with a contribution ratio of 100%. Qualified bid applicants are now invited to participate in the project registration through public tender.

II. Project Overview

1. Project Location: Jiangdu Economic Development Zone, Yangzhou City.

2. Project Content and Scale: This project plans to utilize the existing sites of enterprises within the Jiangdu Economic Development Zone to construct an energy storage power station, with a planned installed capacity of 246MW/492MWh. The lithium iron phosphate (LFP) batteries for the energy storage power station will be arranged in fully prefabricated cabins, with 246 2MWh energy storage battery cabins placed outdoors. The energy storage battery cabins will adopt a 1MW/2MWh cabinet configuration scheme using LFP batteries. Each energy storage battery cabin will be equipped with one 1000kW Power Conversion System (PCS), and each set of energy storage battery cabins will be connected to one 1000kVA local step-up transformer. The PCS and 10kV local step-up transformers will be installed outdoors as complete integrated units.

3. Total Investment for This Project: Approximately 590 million yuan.

4. Planned Construction Period: 365 calendar days.

5. Project Standards: Qualified.

6. Quality Grade Requirements: Qualified.

III. Project Section Division and Tender Content

This tender does not divide the project into sections. The tender content is the construction of the 246MW/492MWh distributed energy storage power station project in Jiangdu Economic Development Zone.

IV. Registration Conditions

1. This tender requires that bidders have corresponding construction capabilities in terms of personnel, equipment, and funding, and meet the following requirements: (1) The ability to independently enter into contracts; (2) The enterprise's qualification category, grade, and the project leader's registered profession and qualification registration comply with relevant national regulations; (3) The enterprise meets safety production conditions and has obtained a safety production license issued by the construction administrative department.

2. The project leader proposed by the bidder must be registered with the bidder's unit and possess a valid safety production assessment certificate (B certificate), and meet the following conditions: (1) The project leader is not concurrently employed or practicing in two or more units; (2) The project leader has no ongoing projects (the project manager has no ongoing projects, and the bidder must provide a signed and stamped commitment letter); (3) The project leader has no record of bribery-related criminal activities, or if there is a record, it has been more than five years since the record date. (4) If, after winning the bid, the bid inviter finds through spot checks that the bid winner is inconsistent with the commitments made during bidding, the bid inviter may determine the second-ranked bid candidate as the bid winner. If the second-ranked bid candidate is disqualified for the same reasons specified in the preceding paragraph or declines to win the bid, the bid inviter may determine the third-ranked bid candidate as the bid winner, and so on.

3. Joint bidding is not accepted for this tender.

Original Title: 1.199 yuan/Wh! Tender for 246MW/492MWh Distributed Energy Storage Power Station in Jiangsu

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
관련 뉴스
[태양광: 방글라데시, 5GW 목표로 순계량 옥상 태양광에 kWh당 0.086달러 요금제 도입]
2시간 전
[태양광: 방글라데시, 5GW 목표로 순계량 옥상 태양광에 kWh당 0.086달러 요금제 도입]
더 보기
[태양광: 방글라데시, 5GW 목표로 순계량 옥상 태양광에 kWh당 0.086달러 요금제 도입]
[태양광: 방글라데시, 5GW 목표로 순계량 옥상 태양광에 kWh당 0.086달러 요금제 도입]
방글라데시 전력부는 자국 순계량 제도에 따라 적격 옥상 태양광 시스템의 잉여 전력에 대해 kWh당 10.50타카(0.086달러)의 요금을 발표했으며, 2030년 2월 28일까지 3년간 유효하다. 배터리 저장장치를 갖춘 옥상 태양광 시스템의 최대 발전 비용은 kWh당 8타카로 설정되었으며, 정부는 20%의 이윤과 11.25%의 프리미엄을 추가했다. 2027년 2월 28일까지 설치되어 2025년 순계량 지침에 따라 적격한 시스템은 인센티브 요금을 받을 수 있다. 정부는 여름철 성수기 수요 시 3GW를 초과하는 일일 전력 부족 문제를 해결하기 위해 내년 여름까지 순계량을 통해 최소 5GW의 태양광 용량을 설치하는 것을 목표로 하고 있다.
2시간 전
[Solar: 호주 프론티어 에너지, 서호주 Waroona 하이브리드 태양광-배터리 프로젝트 계약 체결]
2시간 전
[Solar: 호주 프론티어 에너지, 서호주 Waroona 하이브리드 태양광-배터리 프로젝트 계약 체결]
더 보기
[Solar: 호주 프론티어 에너지, 서호주 Waroona 하이브리드 태양광-배터리 프로젝트 계약 체결]
[Solar: 호주 프론티어 에너지, 서호주 Waroona 하이브리드 태양광-배터리 프로젝트 계약 체결]
프론티어 에너지는 서호주 남서부에 위치한 와루나 재생에너지 프로젝트 1단계의 모든 주요 계약을 체결했다고 발표했다. 이 프로젝트는 132MW 규모의 태양광 발전 시설과 81.5MW/565MWh 규모의 배터리 에너지 저장 시스템으로 구성된다. 론지가 650W 및 655W 정격의 태양광 패널 20만 장 이상을 공급하고, 트리나솔라가 20년 보증 및 장기 서비스 계약에 따라 배터리 유닛을 공급하며, SMA가 인버터를 제공한다. 프로젝트 예산은 약 3억 1천만 달러이며, 이번 달에 착공하여 2028년 첫 전력 생산을 목표로 한다. 향후 태양광 1GW 및 저장 용량 660MW 규모로 확장할 계획이다.
2시간 전
[태양광: 말레이시아, 2.5GW 태양광 및 1.25GW 저장장치를 포함한 LSS6 국가 태양광 프로그램 출범]
2시간 전
[태양광: 말레이시아, 2.5GW 태양광 및 1.25GW 저장장치를 포함한 LSS6 국가 태양광 프로그램 출범]
더 보기
[태양광: 말레이시아, 2.5GW 태양광 및 1.25GW 저장장치를 포함한 LSS6 국가 태양광 프로그램 출범]
[태양광: 말레이시아, 2.5GW 태양광 및 1.25GW 저장장치를 포함한 LSS6 국가 태양광 프로그램 출범]
말레이시아 에너지전환·수자원전환부는 7월에 LSS6 대규모 태양광 입찰을 시작하여 총 2,500MW의 태양광 용량과 1,250MW의 배터리 에너지 저장장치를 결합하고, 부미푸테라 기업을 위해 150MW를 별도 배정했다. 이는 말레이시아 사상 최대 규모의 유틸리티급 태양광 입찰이자, 태양광-ESS 하이브리드 개발을 의무화한 첫 LSS 라운드이다. 이 프로그램은 약 130억~150억 링깃(약 32억~37억 달러)의 민간 투자를 유치할 것으로 예상되며, 프로젝트는 단계적으로 준공되어 2029년 12월 31일까지 완전 상업 운전을 목표로 한다.
2시간 전
1.199 yuan/Wh! Tender for 246 MW/492 MWh Distributed ESS Power Station in Jiangsu - Shanghai Metals Market (SMM)