Latest Progress on the 20,000 mt Silicon Carbon Anode Material Project by Inner Mongolia Guiyuan Xinneng Electronic Materials Technology Co., Ltd.
Inner Mongolia Guiyuan Xinneng Electronic Materials Technology Co., Ltd. is constructing a 20,000 mt silicon carbon anode material project located in the Dalu Industrial Park of Jungar Economic Development Zone. The project commenced construction on May 9, 2024, with a total investment of 2.2 billion yuan and a total land area of 400 mu. The project is planned to have an annual production capacity of 20,000 mt of silicon carbon anode material, and it will be constructed in three phases. Currently, the first phase, with an annual production capacity of 2,000 mt of silicon carbon anode material, is under construction.