Green Hydrogen Project Tracking - Shenneng Inner Mongolia Ejin Horo Banner PV Hydrogen Production Project Passes Special Acceptance

게시됨: Apr 22, 2025 10:33

Recently, the 250 MW PV hydrogen production project of Shenzhen Energy Group Beikong Company in Otog Front Banner passed the special acceptance and successfully obtained the mobile pressure vessel filling license, marking that the project has operational capabilities and can carry out hydrogen filling and external sales.

This project is one of the first batch of wind and solar power hydrogen production demonstration projects in Inner Mongolia Autonomous Region. It uses new energy PV power generation for hydrogen production, adopts alkaline water electrolysis technology, with an annual hydrogen production capacity of over 6,700 mt, and is equipped with corresponding green hydrogen storage and transportation equipment. The produced green hydrogen product has reached an excellent purity level.

Project Basic Information

  • Project Legal Entity: Shenergy North (Otog Front Banner) Energy Development Co., Ltd.

  • Project Name: Otog Front Banner Shanghai Temple Economic Development Zone PV Hydrogen Production Project in Ordos City.

  • Project Address: Shanghai Temple Economic Development Zone, Otog Front Banner, Ordos City, Inner Mongolia.

Project Designed Capacity

The project is designed with an annual hydrogen production capacity of about 6,000 mt. After the completion of the first and second phases, the annual hydrogen production capacity will exceed 6,700 mt, with a hydrogen purity of 99.999%.

Project Construction Content and Scale

Including the construction of a new PV power station with an installed capacity of 250 MW and an average annual power generation of 470 million kWh, as well as a water electrolysis hydrogen production plant with an annual capacity of 6,000 mt and supporting facilities. A hydrogen production and refueling integrated station and corresponding hydrogen energy storage and transportation equipment will also be constructed.

Total Project Investment

The total investment is 1.62 billion yuan, of which 317 million yuan is self-owned funds, and the remaining investment is planned to be solved through financing.

Project Construction Significance and Impact

After the project is put into operation, the average annual power generation will be about 470 million kWh, which can replace about 146,000 mt of standard coal and reduce carbon dioxide emissions by 390,000 mt. The energy-saving and emission-reduction effects are significant. It is of great significance for promoting the implementation of the dual controls on energy consumption and energy intensity in Ordos City, achieving the renewable energy consumption weight target, improving people's livelihood and expanding employment, and promoting high-quality economic development in the region.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn