迎接“531”再度掀起的抢装潮,组件价格或将上涨2-3 cents/W?

게시됨: Feb 12, 2025 17:26
[Another "531" Rush for Installations Expected, PV Module Prices May Increase by 0.02-0.03 RMB/W?] According to industry sources, several dealers have indicated that major PV module producers are preparing for a price increase, with a range of 0.02 RMB/W to 0.03 RMB/W. In response, Polaris conducted a survey of some module enterprises. A few top-tier enterprises confirmed the situation, while others explicitly stated that there are currently no plans to adjust prices, with the overall stance of enterprises being one of observation. (Polaris Solar PV Network)

According to industry sources, several dealers have indicated that major PV module producers are preparing for price increases, with a range of 0.02 yuan/W to 0.03 yuan/W. In response, Polaris conducted a survey of some module companies. A few top-tier enterprises confirmed the situation, while others explicitly stated that they currently have no plans to adjust prices, with the overall attitude of the companies being one of observation.

The main driver of this new round of module price increases is the "Notice on Deepening the Market-Oriented Reform of New Energy On-Grid Tariffs to Promote High-Quality Development of New Energy" (hereinafter referred to as the "Notice") issued by the National Development and Reform Commission (NDRC) and the National Energy Administration on February 9.

PV Faces Another Rush for Installations

According to the "Notice," the on-grid electricity generated by wind and solar power will, in principle, fully enter the electricity market, with on-grid tariffs formed through market transactions. For electricity included in the mechanism, the portion of the market transaction price that is lower or higher than the mechanism tariff will be settled by power grid enterprises according to regulations, with the settlement costs included in the local system operation costs, i.e., "refunds for overcharges and supplements for undercharges."

The "Notice" stipulates that June 1, 2025, will serve as the period dividing new and existing projects. For existing projects commissioned before June 1, 2025, tariff differences will be settled to ensure proper alignment with current policies. The electricity volume will be aligned with existing policies that guarantee relevant electricity volumes. Within the scale, new energy projects will independently determine the proportion of electricity subject to the mechanism each year, but it must not exceed the previous year's proportion. The mechanism tariff will follow current pricing policies and will not exceed the local benchmark price for coal-fired power.

This means that projects connected to the grid before June 1 can enjoy more "guaranteed" tariffs, which will fall between the local desulfurized coal benchmark tariff and the spot price.

For incremental projects commissioned on or after June 1, 2025, the electricity volume included in the mechanism will be dynamically adjusted based on the completion of new energy development targets set by the state for each region. The mechanism tariff will be determined through market-based bidding by each region.

This indicates that for projects connected to the grid after June 1, the revenue calculation model will undergo significant changes. Following the release of the document, there is still no clear understanding among stakeholders regarding the actual settlement tariff calculation method for projects. Considering the operational challenges, completing grid connection before June 1 is seen as a safer and more prudent option, leading to another "531" rush for installations in the PV sector.

Regarding distributed PV projects, only Shandong and Hebei have introduced policies for distributed PV power generation to enter the market. Industry insiders analyzed that before June, relevant provinces will likely continue implementing current provincial policies. Afterward, they may formulate specific implementation details in line with national policies, such as clarifying whether rooftop PV projects will have special policies and the bidding model for distributed projects.

However, to avoid complex revenue calculations and market bidding rules, some distributed projects with better investment returns are also highly likely to participate in the "531" rush for installations.

Other industry insiders suggested that for distributed PV projects entering the market, the strategy of prioritizing commercial projects over household PV projects may continue. Household PV projects may be the last to enter the market and may not necessarily participate in this rush for installations.

Can Modules Achieve the Desired Price Increase?

The rush for installations in H1 has created an atmosphere for module price increases, but whether modules can achieve the expected price increase remains a topic of differing opinions. Observations from social media show that some dealers are still promoting modules, covering brands across multiple tiers. Currently, second- and third-tier companies are observing the actions of top-tier enterprises, with a tendency of "if you raise prices, so will we." However, some companies believe that it depends on end-use demand and caution against being overly optimistic.

On one hand, 2025 marks the final year of the 14th Five-Year Plan. According to statistics from Polaris Solar PV Network, nine regions have yet to meet their targets, with Shanxi and Guizhou each falling short by over 10 GW. These regions may accelerate the advancement of PV projects in 2025.

On the other hand, considering the comprehensive market entry policy for new energy projects, the revenue calculation model for PV project investments has undergone significant changes, potentially affecting companies' investment willingness.

Considering the supply and demand situation, the China Photovoltaic Industry Association previously analyzed that the annual capacity of all PV segments currently exceeds 1,100 GW, while the optimistic demand for the global and Chinese PV markets in 2025 is only 600 GW and 250 GW, respectively. The supply-demand imbalance remains unresolved.

From the perspective of the industry chain prices, the polysilicon market price remains stable. According to the Silicon Industry Association, downstream wafer companies are expected to increase their production schedules, leading to a steady growth in polysilicon demand. However, the increase in wafer production schedules carries the risk of converting into inventory, making it challenging to maintain prices in the short term. The acceptance of continuous price increases for polysilicon remains weak.

Data from the January module centralised procurement winning bids this year shows that the average winning bid price for n-type modules was approximately 0.696 yuan/W, a slight increase MoM. The recently announced winning bid results for CGN New Energy's 2025 PV module equipment framework procurement package 1 (sections 2, 3, and 4) indicate module winning bid prices ranging from 0.695 to 0.706 yuan/W.

As for whether PV module prices will continue to rise, the upcoming bidding for the Datang module centralised procurement project may provide insights into the trend.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
관련 뉴스
[SMM PV 뉴스] 해발 4,700미터! 티베트 야를룽짱부강 중하류 최대 태양광 프로젝트 완공.
16시간 전
[SMM PV 뉴스] 해발 4,700미터! 티베트 야를룽짱부강 중하류 최대 태양광 프로젝트 완공.
더 보기
[SMM PV 뉴스] 해발 4,700미터! 티베트 야를룽짱부강 중하류 최대 태양광 프로젝트 완공.
[SMM PV 뉴스] 해발 4,700미터! 티베트 야를룽짱부강 중하류 최대 태양광 프로젝트 완공.
최근 중국전건이 건설한 티베트 취쑹현 뤄부사 태양광 프로젝트 1단계 850MW가 준공 검수를 성공적으로 통과해 지역 전력 수급 긴장 완화와 고원 에너지 공급 장벽 강화에 중요한 지원을 제공했다. 티베트 취쑹현 뤄부사 태양광 프로젝트는 부지 면적이 약 4,289.59무, 총 설치 용량 850MW로, 티베트 야중 청정에너지 기지의 첫 번째 중점 상업용 태양광 프로젝트이자 야장강 중하류 최대 규모의 태양광 청정 발전 프로젝트다. 이 프로젝트는 4개 단계로 개발되며, 1단계는 200MW, 평균 해발 4,700m에 위치한다. 중국전건 청두원이 220kV 승압 변전소, 50MW 태양광 구역, 20.74km 송전선로 및 대측 변전소 확장 공사를 맡았고, 중국수리수전 제9공정국이 150MW 태양광 발전 구역 건설을 맡아 총 348,000장의 태양광 모듈과 64대의 박스형 변압기, 704대의 인버터를 설치했다.
16시간 전
[SMM PV 뉴스] 미국 에너지부(DOE), 우주 태양광 기술 개발에 1,200만 달러 투자
16시간 전
[SMM PV 뉴스] 미국 에너지부(DOE), 우주 태양광 기술 개발에 1,200만 달러 투자
더 보기
[SMM PV 뉴스] 미국 에너지부(DOE), 우주 태양광 기술 개발에 1,200만 달러 투자
[SMM PV 뉴스] 미국 에너지부(DOE), 우주 태양광 기술 개발에 1,200만 달러 투자
8월 31일, 미국 에너지부(DOE)는 총 1,200만 달러 규모의 새로운 우주 태양광 연구개발 자금 지원 기회를 발표했다. 이 발표는 목표를 명확히 밝히고 있다. 우주용 태양전지 및 모듈 비용 절감, 미국 내 제조 역량 확대, 우주 또는 근우주 환경에서의 제3자 검증을 위한 시제품 개발 촉진이 그것이다.
16시간 전
[SMM PV 뉴스] 유럽 벤치마크 구축 | 치코 솔라 에너지 이탈리아 221MW 추적 시스템 프로젝트 공식 착수
16시간 전
[SMM PV 뉴스] 유럽 벤치마크 구축 | 치코 솔라 에너지 이탈리아 221MW 추적 시스템 프로젝트 공식 착수
더 보기
[SMM PV 뉴스] 유럽 벤치마크 구축 | 치코 솔라 에너지 이탈리아 221MW 추적 시스템 프로젝트 공식 착수
[SMM PV 뉴스] 유럽 벤치마크 구축 | 치코 솔라 에너지 이탈리아 221MW 추적 시스템 프로젝트 공식 착수
최근 신헝위안 에너지는 221MW 추적식 지지대 벤치마크 프로젝트를 공식 가동했다. 이 프로젝트는 기업이 유럽 지역에서 수주한 핵심 단일 프로젝트로, 회사의 중국 외 시장 전략적 확장에 있어 중요한 돌파구를 의미한다. 이는 현지 저탄소 에너지 발전을 크게 촉진하고 지역의 녹색 에너지 전환에 강력한 동력을 불어넣고 있다.