【Jiayuguan Electrolytic Cell Full-Graphite Green Carbon Reduction Renovation Project】 Recently, at the site of the fifth phase of the Jiayuguan Electrolytic Cell Full-Graphite Green Carbon Reduction Renovation Project, the final 328 sets of 500KA full-graphite electrolytic cells in Jiayuguan are being optimized and renovated in an orderly manner. The fifth phase of the project was officially started on May 30th, and according to the planned schedule, 76 sets of electrolytic cells can be completed by the end of 2024.