On September 12th, the Qinhuangdao Municipal Administrative Approval Bureau accepted the application for the establishment of the 200MW wind power project - Yuanwang Hechu Integration Project in Changli County and completed the approval and reply.
It is reported that the project is planned to invest 1.2 billion yuan, install 36 wind turbines, with a total capacity of 200MW, build a 220kV booster station with a scale of 1 turn, and temporarily build a storage station. After the completion of the project, the annual power generation can reach 472 million kWh.