In the second quarter, a number of large-scale polysilicon projects will be put into operation, and the output will increase significantly in April and May as the production capacity ramps up.
These include a number of major projects in Xinjiang, Sichuan, and Inner Mongolia, with a total production capacity of 318,000 mt. The domestic polysilicon supply is expected to increase significantly to around 350,000 mt in the second quarter.
However, production reductions are likely to occur in the second half of the second quarter.
The main reason is that the current water level in west China is relatively low. Possible power rationing during the low-water period this year combined with concentrated maintenance will slow the output growth. Then the supply will be less than expected.
![[SMM PV 뉴스] 해발 4,700미터! 티베트 야를룽짱부강 중하류 최대 태양광 프로젝트 완공.](https://imgqn.smm.cn/usercenter/rnXTf20251217171741.jpg)
![[SMM PV 뉴스] 미국 에너지부(DOE), 우주 태양광 기술 개발에 1,200만 달러 투자](https://imgqn.smm.cn/usercenter/ZbnfH20251217171741.jpg)
![[SMM PV 뉴스] 유럽 벤치마크 구축 | 치코 솔라 에너지 이탈리아 221MW 추적 시스템 프로젝트 공식 착수](https://imgqn.smm.cn/usercenter/GOtTW20251217171740.jpg)