Indonesia’s NPI out went up in June amid expanded production of Tsingshan

게시됨: Jul 15, 2021 13:58 (GMT+8)
NPI output in Indonesia stood at 77,000 mt in metal content in June, up 4.34% on the month and 65.7% on the year, with accumulated output at 426,000 mt in Ni content in 2021. There are 3 new production lines in June, 2 in Qingshan XiaoK park and 1 in Delong.

SHANGHAI, Jul 15 (SMM) - NPI output in Indonesia stood at 77,000 mt in metal content in June, up 4.34% on the month and 65.7% on the year, with accumulated output at 426,000 mt in Ni content in 2021. There are 3 new production lines in June, 2 in Qingshan XiaoK park and 1 in Delong.

Indonesia Tsingshan has put 40 NPI RKEFs into operation in Morowali as of the beginning of June. On January 30, a production line that switched from silico-manganese to NPI began to yield product. The first production line of a joint venture project by Walsin Lihwa and Tsingshan yielded product on January 31, the second production line yielded product on February 9, and the third production line yielded product in early May. DaK yield product of 40 bars. Another lines of Walsin Lihwa may be put into production in July. It is also expected that the four production lines of Haitian Nickel will also be put into operation in H2 2021.

Indonesia Tsingshan plans to expand the total number of RKEFs in the Weda bay area to 44 units, of which 12 units were put into production in 2020. 24 production lines have been commissioned. It commission 18 RKEFs in 2021 to bring the total number of production lines in operation to 30. Among them, 2 RKEFs of a joint venture by Blue Sky Nickel and Punp in Wedabay D District were put into production in January and another two RKEFs were commissioned in March. Four production lines in District E were also commissioned (1 line was commissioned in January, 1 line in February, and 2 lines in March). 2 production lines of Fengli Metals in F District were commissioned in late May; and the 2 ferronickel production lines of Qingtian Nickel Industry in F District were also put into production in mid-June and the end of June respectively. Tsingshan plans to put another 6 production lines into production before the end of the year. Power restrictions in the second phase of Xiao K Park has not been completely resolved. The production capacity of the production line in the early stage has not been fully released. It is expected that the problem may be gradually resolved in July. In addition, a production line in the first phase of the Wedabay Park implemented maintenance due to the addition of cold calcined sand, and the affected output stood at 1,500 mt.

Indonesia Delong’s Phase II project commissioned 15*33000KVA production lines in 2020, of which the 15th line yielded product in January 2021. It is estimated that there are still 20 furnaces to be commissioned in 2021. Two new production lines have been added in May, and one line in June. At present, there are 33 production lines in the first and second phases. The remaining 17 lines will be commissioned in H2.

4 sets of 33000KVA RKEFs of Jinchuan WP operated normally in May and 4 sets of 33000KVA RKEFs of Xinxing Ductile Iron Pipes saw daily output of 500 mt with normal production. Two sets of BF with 80 cubic meters of Xinhualian implemented maintenance due to the high cost of coke. At present, two sets of BF with 80 cubic meters maintained production, producing medium-grade ferronickel with an average grade of about 7%; Indoferro's two 16500KVA submerged arc furnaces continued to operate at low yields; In response to the pandemic in Indonesia, two new lines originally planned to be commission at the end of June delayed until late July; PT. Cahaya Modern Metal Industri resumed production in early 2021, with a monthly output of about 2,000 mt and a grade of about 12%. PT.BTS Iron production has also resumed recently. In summary, in addition to the release of new capacity in July, the removal of power restrictions problem has also brought about an increase in the operating rates of some production lines. It is estimated that Indonesia’s ferronickel output will record 83,500 mt in metal content in July, a month-on-month increase of 8.5% and a year-on-year increase of 69.5%.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
관련 뉴스
[SMM 니켈 속보] 인도네시아 업데이트 — 2026년 10월 5일
1시간 전
[SMM 니켈 속보] 인도네시아 업데이트 — 2026년 10월 5일
더 보기
[SMM 니켈 속보] 인도네시아 업데이트 — 2026년 10월 5일
[SMM 니켈 속보] 인도네시아 업데이트 — 2026년 10월 5일
인도네시아 니켈 광석 CIF 평균 가격은 대체로 안정세를 유지했으며, SMM 최신 평가는 다음과 같다. Ni 1.2%: CIF 가격 $25.5/wmt, 변동 없음 Ni 1.3%: CIF 가격 $27.5/wmt, 변동 없음 Ni 1.4%: CIF 가격 $48.7/wmt, 변동 없음 Ni 1.5%: CIF 가격 $54.2/wmt, 변동 없음 Ni 1.6%: CIF 가격 $59.0/wmt, 변동 없음 상류 시장에서는 추가 RKAB 쿼터가 점진적으로 시장에 유입되고 판매자들의 가격 조정 압력이 커지면서 니켈 광석 가격이 9월 말 대비 약세를 보였다. SMM에 따르면 할인이 공식적으로 나타나기 시작했으며, 일부 광석 가격은 HPM 기준가 아래로 하락했다. 한편, 10월 상반기 니켈 HMA는 $16,322.67/mt로 하향 조정되어 9월 하반기 HMA $16,698/mt 대비 $375.33/mt, 즉 2.25% 하락했다.
1시간 전
【SMM 니켈 속보】10월 5~11일 니켈 기상 리스크는 관리 가능한 수준 유지
1시간 전
【SMM 니켈 속보】10월 5~11일 니켈 기상 리스크는 관리 가능한 수준 유지
더 보기
【SMM 니켈 속보】10월 5~11일 니켈 기상 리스크는 관리 가능한 수준 유지
【SMM 니켈 속보】10월 5~11일 니켈 기상 리스크는 관리 가능한 수준 유지
필리핀, 인도네시아, 중국의 주요 니켈 생산 및 물류 지역의 기상 상황은 10월 5일~11일 전반적으로 양호할 것으로 예상되나, 국지적 기상 현상으로 인해 단기적인 운영 차질이 발생할 수 있다. 필리핀에서는 10월 6일~7일 팔라완과 수리가오에 산발적인 비와 뇌우가 예상되며, 10월 8일~9일에는 동비사야스와 민다나오에 강우량이 증가하여 광산 도로 운송, 광석 바지선 운항 및 선박 적재에 일시적인 위험이 있을 수 있다. 인도네시아에서는 모로왈리와 코나웨가 비교적 안정적인 상태를 유지할 것으로 예상되며, 강우량이 적고 뚜렷한 폭풍 활동은 없을 전망이다. 할마헤라와 오비에서는 간헐적인 비와 강한 바람이 예상되어 해상 물류에 일시적인 영향을 미칠 수 있다. 중국에서는 주요 니켈 광석 수입항이 대체로 정상 운영될 것으로 예상되나, 국지적인 비와 강한 바람으로 인해 선박 하역 및 화물 운송에 짧은 지연이 발생할 수 있다.
1시간 전
[SMM 니켈 플래시 뉴스] 모로왈리 PT Askon 소요 사태로 우려 확산
5시간 전
[SMM 니켈 플래시 뉴스] 모로왈리 PT Askon 소요 사태로 우려 확산
더 보기
[SMM 니켈 플래시 뉴스] 모로왈리 PT Askon 소요 사태로 우려 확산
[SMM 니켈 플래시 뉴스] 모로왈리 PT Askon 소요 사태로 우려 확산
10월 2일, 인도네시아 중부 술라웨시 주 모로왈리 현 마타라페 마을에 위치한 PT Astima Konstruksi(PT Askon)에서 광산 분진 및 환경 영향과 관련된 시위가 소요 사태로 확대되었다. 현지 언론에 따르면 시위대가 차량 여러 대와 굴착기를 불태웠으며, 회사의 운반 도로와 부두 접근이 차단되어 자재 운송이 중단되었다. 이후 경찰은 현장에서 중국 국적자를 대피시켰다. 이번 사건으로 인근 니켈 채굴 및 물류 활동의 차질 가능성에 대한 우려가 제기되었다. 다만 10월 5일 기준으로 특정 니켈 광산의 생산 중단 또는 감축 규모를 확인한 보고는 아직 없다. 운송 접근성 회복, 현지 치안 상황, 그리고 니켈 광석 공급에 대한 후속 영향에 지속적인 주의가 필요하다.
5시간 전