SHANGHAI, Mar. 22 (SMM) – Tsingshan Group has put online its whole phase two project, with total capacity of 60,000-tpy (metal content), in Indonesia recently, SMM learns.
Tsingshan Group started production at its phase two project last December, but power supply issues restricted its production capacity, only 30,000-tpy capacity online.
This March, the Group succeeded to produce from the rest of the project, SMM learns.
Tsingshan Group started its trial production at its phase one project in January 2015, producing 20,000 tonnes (metal content) over the year, and will complete construction of phase three project in 2017, according to its plan.