Forecast of Polysilicon Capacity Commissioning [SMM Analysis]

Telah Terbit: Jul 2, 2024 14:27
Since 2024, the main materials in the photovoltaic sector have been severely impacted by overcapacity, leading to a continuous decline in overall prices. Polysilicon industry has now sufferred industry-wide losses...

Since 2024, the main materials in the photovoltaic sector have been severely impacted by overcapacity, leading to a continuous decline in overall prices. Polysilicon industry has now sufferred industry-wide losses...

According to SMM's current tracking of 24 domestic companies' production lines, about five companies have completely shut down. Overall, this has had a minimal impact on polysilicon supply.

The reduction in polysilicon output mainly comes from the decreased operating rates of other companies, with some even maintaining only low-load operations. These companies have contributed significantly to the reduction.

Regarding future polysilicon capacity commissioning, SMM has learned that due to current cash flow and market pressures, many well-known projects have chosen to delay construction or production. The market reshuffle has quietly begun.

Meanwhile, even overseas capacities are not immune. According to SMM, due to their own cost-effectiveness and the impact on downstream capacities in Southeast Asia, overseas polysilicon sales to China have experienced some degree of stagnation. In July, some manufacturers have already reduced production, with total overseas output dropping from around 8,000 mt to 5,000-6,000 mt.

H2 2024 has already begun. SMM believes that with the reduction in polysilicon supply projects, there will indeed be some relief in supply pressure. However, as of now, H2 polysilicon output is expected to reach around 900,000 mt. The polysilicon industry surplus still exists, and the capacity elimination of producers will continue in H2.

Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn
Berita Terkait
[SMM Berita PV] Di ketinggian 4.700 meter! Proyek PV terbesar di bagian tengah dan hilir Sungai Yarlung Zangbo di Tibet telah selesai dibangun.
15 jam yang lalu
[SMM Berita PV] Di ketinggian 4.700 meter! Proyek PV terbesar di bagian tengah dan hilir Sungai Yarlung Zangbo di Tibet telah selesai dibangun.
Baca Selengkapnya
[SMM Berita PV] Di ketinggian 4.700 meter! Proyek PV terbesar di bagian tengah dan hilir Sungai Yarlung Zangbo di Tibet telah selesai dibangun.
[SMM Berita PV] Di ketinggian 4.700 meter! Proyek PV terbesar di bagian tengah dan hilir Sungai Yarlung Zangbo di Tibet telah selesai dibangun.
Baru-baru ini, PLTS Luobusha Fase I berkapasitas 850 MW di Kabupaten Qusum, Tibet, yang dibangun oleh PowerChina, berhasil lolos uji terima penyelesaian, memberikan dukungan penting untuk meredakan ketegangan pasokan-permintaan listrik regional dan memperkuat benteng pasokan energi dataran tinggi. PLTS Luobusha di Kabupaten Qusum, Tibet, mencakup area sekitar 4.289,59 mu, dengan total kapasitas terpasang 850 MW. Ini merupakan gelombang pertama proyek PLTS komersial utama di Basis Energi Bersih Yazhong di Tibet dan proyek pembangkit listrik bersih PLTS terbesar di bagian tengah dan hilir Sungai Yajiang. Proyek ini dikembangkan dalam empat fase, dengan Fase I berkapasitas 200 MW dan elevasi rata-rata 4.700 meter. Chengdu Engineering Corporation di bawah PowerChina melaksanakan pembangunan stasiun penguat 220 kV, area PLTS 50 MW, jalur transmisi 20,74 km, dan perluasan gardu induk di sisi berlawanan; Sinohydro Bureau 9 melaksanakan pembangunan area ladang PLTS 150 MW, memasang total 348.000 modul PLTS, beserta 64 transformator tipe kotak dan 704 inverter.
15 jam yang lalu
[SMM Berita PV] Departemen Energi AS (DOE) Investasikan $12 Juta untuk Mengembangkan Teknologi PV Luar Angkasa
15 jam yang lalu
[SMM Berita PV] Departemen Energi AS (DOE) Investasikan $12 Juta untuk Mengembangkan Teknologi PV Luar Angkasa
Baca Selengkapnya
[SMM Berita PV] Departemen Energi AS (DOE) Investasikan $12 Juta untuk Mengembangkan Teknologi PV Luar Angkasa
[SMM Berita PV] Departemen Energi AS (DOE) Investasikan $12 Juta untuk Mengembangkan Teknologi PV Luar Angkasa
Pada 31 Agustus, Departemen Energi AS (DOE) mengumumkan peluang pendanaan riset dan pengembangan PV luar angkasa baru dengan total hingga $12 juta. Pengumuman tersebut menyatakan tujuannya secara jelas: menurunkan biaya sel surya dan modul untuk aplikasi luar angkasa, memperluas kapasitas manufaktur domestik di AS, dan memajukan prototipe menuju validasi pihak ketiga di lingkungan luar angkasa atau dekat luar angkasa.
15 jam yang lalu
[SMM Berita PV] Membangun Patokan Eropa | Proyek Sistem Pelacak 221 MW Chiko Solar Energy di Italia Resmi Diluncurkan
15 jam yang lalu
[SMM Berita PV] Membangun Patokan Eropa | Proyek Sistem Pelacak 221 MW Chiko Solar Energy di Italia Resmi Diluncurkan
Baca Selengkapnya
[SMM Berita PV] Membangun Patokan Eropa | Proyek Sistem Pelacak 221 MW Chiko Solar Energy di Italia Resmi Diluncurkan
[SMM Berita PV] Membangun Patokan Eropa | Proyek Sistem Pelacak 221 MW Chiko Solar Energy di Italia Resmi Diluncurkan
Baru-baru ini, Xin Hengyuan Energy resmi meluncurkan proyek benchmark dukungan pelacakan 221 MW. Proyek ini merupakan proyek tunggal utama yang dikerjakan oleh perusahaan di kawasan Eropa, menandai terobosan penting dalam ekspansi strategis perusahaan ke pasar di luar Tiongkok. Hal ini secara signifikan memajukan pengembangan energi rendah karbon setempat dan memberikan dorongan kuat bagi transisi energi hijau di kawasan tersebut.
15 jam yang lalu